Report for February 2017

Report Date
February 2017
Report by Muriel Mewissen on behalf of Alan Gilchrist (MVMLAT Programme Managers)
for Sheila Lodge (MVMLAT Portfolio Owner)
and Paul Clark (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During February, work has progressed well across most projects in the programme.

The overall status of the MVM Learning and Teaching programme is AMBER due to delays in closure to MVM032 Speedwell Service Implementation

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - February 2017

 

Section Two: Projects Not Started

Another 16 projects may start later this year, these are:

Project Programme Manager's Commentary
MVM102 Innovative Technology Review  
MVM103 Mobile Device Management  
MVM104 Strategy for the upgrade of our computer labs (annual)  
MVM106 Student Print Strategy  
MVM108 Technology to support Attendance and Monitoring  
MVM109 Technology to support communications with potential students  
MVM110 Technology to support Open Educational Resources (OER)  
MVM112 Technology to support simulation teaching  
MVM113 Technology to support student portfolios  
MVM114 Technology to timetabling and room booking  
MVM116 Video Strategy  
MVM117 Virtual Desktop and software access  
MVM118: Deployment of an online application to support assessment and feedback for MBChB To start in April 2017
MVM119: Data Migration and Data Creation for the online assessment and feedback application for MBChB To start in April 2017
MVM121: Assessment and Feedback Reporting In the process of being prioritised
MVM122: Biomedical Sciences submission word count facility To start in March 2017

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

MVM032: Speedwell Service Implementation

Category: Discretionary

 

Milestones
Target Date Title
24-Mar-17 Closure
 
RAG Status

AMBER

Report by Tim Gray for February 2017

Achievement this period
  • No achievements this period
Issues
  • Project closure delayed due to PM's sick leave
Next Steps
  • Publish EqIA
  • Closure

 

MVM101: Connectivity - on-campus and off-campus

Category: Discretionary

 

Milestones
Target Date Title
31-Jul-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for February 2017

Achievements:
  • No progress has been made in finalising a meeting date with NHS Forth Valley to discuss implementing eduroam with them.
Issues:
  • We are still waiting for suitable dates from NHS Lanarkshire as to when the consultant can come on site to help set up the connection. 
Next Steps:
  • We will continue to chase this up.

 

MVM105:

Strategy for upgrade of our teaching spaces (annual)

 

Category Discretionary

 

Milestones
Target Date Title
30-Jun-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for February 2017

Vet School:
  • Four AV contractors have responded to the tender.  These have been scored by the Learning Spaces Technology team and are currently with the procurement department for approval.  Once we know who the appointed contractor is and the associated costs, we will confirm if all of the rooms can be upgraded this year.
Central Area:
  • PG Viva room has been identified as G32 in the Hugh Robson Building (old LTS offices).  Room has recently been painted bright white, so will need to be repainted to allow VC camera to work correctly.
Chancellor's Building:
  • Drawing have been created for all rooms and we are aiming to send the tender documentation to procurement during week beginning 13th March. 
  • An invitation to evaluate the 4K touchscreen was sent out to the most frequent bookers of lecture theatre A, however no one responded or showed up.  The decision to go ahead with its installation was therefore made by Alan Gilchrist.
  • Minor works orders have been sent to engie for the two microlabs and SU209.

 

MVM107:

Procurement of an online application to support assessment and feedback for MBChB

Category: Discretionary

 

Milestones
Target Date Title
31-Mar-17

Selection Complete

28-Apr-17 Aware Contract Milestone
26-May-17 Project Completion Milestone
 
RAG Status

GREEN

Report by Paul De'Ath for February 2017

Achievements this period
  • All five suppliers delivered hands on demonstration s, completing them by February 27, 2017
  • These were fully attended by the core members of the Project Team covering all areas other than Student engagement (unable to attend due to exams)
  • The Award system has been loaded with all the supplier feedback and access provided - scoring has commenced
  • Two milestones achieved: New Project Initiated to progress Implementation and Evaluation Demonstrations Complete
Issues
Next Steps
  • Scheduled two consensus meetings, Finance meeting TBC by Procurement
  • The Project team will continue marking the supplier responses via Award
  • Additional projects have been prepped with MVM119 likely to be initiated this month

 

MVM111:

Technology to support short-notice communications to students

Category: Discretionary

 

Milestones
Target Date Title
31-Jul-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for February 2017

Achievements this period
  • Alan Gilchrist has been given administrator access to the Connecttxt service and briefly demoed the system to Lydia Crow.
Issues

Certain concerns have been noted:

  • A policy needs to be set on how MBChB will use the service (i.e. who will initiate the texts to the students, if it's an admin team, how will the clinicians inform them etc...)
  • The groups need to be set up in the system from scratch, but can be done via a CSV upload.  The group structure will be complex and the person initiating the text will need to know which specific group to send it to.
  • Need to create an opt-in form which will be sent to the students, so that they can confirm whether they want their mobile number to be used with the service.  An update details form will also need to be created in case students change the mobile phone number.
  • User account structure within the Connecttxt service will need to be created one the policy for its use within MBChB has been confirmed (first point above).
Next Steps
  • The long term future of the service is still uncertain due to the University wide project to look at a notification service.  Paul Clark and Alan Gilchrist have asked for a meeting with the Martin Morrey to discuss MVM being at the 'front of the queue' with some of this work.

MVM115:

Technology to support TransNational Education (TNE)

Category: Discretionary

 

Milestones
Target Date Title
17-Mar-17  Project Brief signed off
18-Aug-17 Delivery complete
20-Oct-17 Complete closure report
 
RAG Status

GREEN

Report by Paul De'Ath for February 2017

Achievements this period

Issues

Next Steps

  • Schedule a meeting between Student Systems and the Technical team who implemented a change in December 2016, to understand what further testing is required
  • Complete draft Project Brief and then seek sign off

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
MVM024 Integration and adoption of ISFM This project started in 15/16 project, and was suspended in May 2016. This project was closed in January 2017. Any remaining activities will be completed as part of MVM120 Windows 10 rollout to computer labs within the Windows 10 Upgrade for Managed Desktops (W10).  