Report for August 2024
- Report Date
- August 2024
Report by Susan Ridder-Patrick (MVMLAT Programme Manager) for Alex Laidlaw (MVMLAT Programme Owner) and Anne-Marie Coriat (MVM Portfolio Owner)
Distribution:
-
Vet and Medical School sub-group IT meeting
-
College Administration Team (CAT) meeting
-
College Undergraduate Learning and Teaching (CULT) committee
-
Post Graduate Learning and Teaching (PGLTC) committee
-
Excerpts taken into CSG report
Section One: Programme Commentary, RAG and Resources Update
Commentary
Programme status: The overall status of the MVMLAT programme for August is RED due to:
- Upgrading of teaching spaces 23/24 project (MVM159) continuing to be impacted by infrastructure delays
- Programme does not have development resource assigned to start new projects
There are seven open programme risks in August:
- Risk 10 - GREEN: Industrial action at the University from November 2021
- Risk 12 - GREEN: Learning Technologists Resourcing
- Risk 13 - RED: Risk to programme from changes to financial budgeting and accounting
- Risk 14 - RED: Late request for large cohorts for online exams
- Risk 15 - GREEN: Impact from Curriculum Transformation Programme unclear
- Risk 16 - RED: Insufficient budget/resourcing capacity for 23/24 work
- Risk 17 - RED: ITI CIS Staff availability
Project highlights
- MVM157: GREEN - No updates this month due to other priorities and return of Medical and Veterinary students.
- MVM158: SUSPENDED until 23 September 2024
- MVM159: RED - Project remains at RED due to the continued delays with infrastructure work
- MVM160: CLOSED in August
- MVM162: GREEN - Planned visit to St Andrews is being rescheduled
- MVM163: GREEN - No updates due to other priorities in getting ready for teaching.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Forward Look - August 2024
Section Two: Projects Not Started
Project | Programme Manager's Commentary |
Upgrading of Teaching Spaces 24/25 (MVM164) | To start in September 2024 |
Student competency (MVM161) | No start date agreed in 24/25 due to resource limitations |
Review of Vet EMS system | No start date agreed in 24/25 due to resource limitations |
BMS portal for PG staff | No start date agreed in 24/25 due to resource limitations |
Section Three: Projects in Progress
MVM Learning and Teaching Projects Update
MVM157 Medical Simulation - Electronic Systems RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM158 Student Placements RAG Status: SUSPENDED until 23 September 2024 No reporting while project is suspended |
|
MVM159 Upgrading of teaching spaces 23/24 RAG Status: RED Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM162 Anatomy Database RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM163 EPPSAT and Simulated Patient Databases RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
Projects outwith the MVM Portfolio Update
SAC105 Adapting ESC (Extensions and Special Circumstances) to support policy changes - RAG Status: GREEN Achievements in Last Period
Issues
Next Steps
|
|
SCP004 Short Course Platform: Operational and Management Reporting - RAG Status: SUSPENDED No reporting while project is suspended |
|
SCP007 Short Course Platform: Payment Integration and PCI-DSS Compliance - RAG Status: SUSPENDED No reporting while project is suspended |
|
SCP008 Short Course Platform: Configuration of Email, SSO and IDM - RAG Status: AMBER Achievements this period:
Next steps:
Risks/Issues:
|
Section Four: Closed or Withdrawn Projects
Only those projects closed from August 2023 onwards are included in this table. A full history of completed projects is available on the programme's website.
Project Info | Project Manager's Commentary |
MVM148 Upgrading of teaching spaces 2021/22 | This project started in November 2021 and closed on 31 August 2023. The Closure Report is available to view. |
MVM153 Upgrading of student computer labs, teaching and meeting room PCs 2022/23 | This project started in September 2022 and closed on 31 August 2023. The Closure Report is available to view. |
MVM155 BMS Honours Portal | This project started in November 2022 and closed on 5 December 2023. The Closure Report is available to view. |
MVM154 Upgrading of teaching spaces 2022/23 | This project started in September 2022 and closed on 5 February 2023. The Closure Report is available to view. |
MVM160 Upgrading of student computer labs, teaching and meeting room PCs 23/24 | This project started in October 2023 and closed in August 2024. The Closure Report is available to view. |
Section Five: Programme Meeting Minutes
Notes and actions for all programme meetings are available on the MVMLAT website. Only the most recent five meetings' direct links are included in this table:
Date | Notes and actions |
15 August 2024 | Programme Review Monthly Meeting - July 2024 |
18 July 2024 | Programme Review Monthly Meeting - June 2024 |
13 June 2024 | Programme Review Monthly Meeting - May 2024 |
16 May 2024 | Programme Review Monthly Meeting - April 2024 |
15 April 2024 | Programme Review Monthly Meeting - March 2024 |
Section Six: MVM Portfolio Projects Update
The MVM Portfolio contains three programmes: CMVM Learning and Teaching - MVMLAT (this programme); CMVM Business Administration - MVMBUS and CMVM Research - MVMRES. Information on current work in MVMBUS and MVMRES are available on the following websites: