Report for March 2017

Report Date
March 2017
Report by Muriel Mewissen on behalf of Alan Gilchrist (MVMLAT Programme Managers)                             
for Sheila Lodge (MVMLAT Portfolio Owner)
and Paul Clark (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During March, good progress were made across the MVM Learning and Teaching programme.

Two new projects have started this month:

One project was closed:

The overall status of the MVM Learning and Teaching programme is AMBER due to delays in MVM105: Strategy for upgrade of our teaching spaces (annual).

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - March 2017

 

Section Two: Projects Not Started

Another 14 projects may start later this year, these are:

Project Programme Manager's Commentary
MVM102 Innovative Technology Review  
MVM103 Mobile Device Management  
MVM106 Student Print Strategy  
MVM108 Technology to support Attendance and Monitoring  
MVM109 Technology to support communications with potential students  
MVM110 Technology to support Open Educational Resources (OER)  
MVM112 Technology to support simulation teaching  
MVM113 Technology to support student portfolios  
MVM114 Technology to timetabling and room booking  
MVM116 Video Strategy  
MVM117 Virtual Desktop and software access  
MVM118: Deployment of an online application to support assessment and feedback for MBChB To start in May 2017
MVM119: Data Migration and Data Creation for the online assessment and feedback application for MBChB To start in April 2017
MVM121: Assessment and Feedback Reporting To start in April 2017

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

MVM101: Connectivity - on-campus and off-campus

Category: Discretionary

 

Milestones
Target Date Title
31-Jul-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for March 2017

Achievements:

No major updates to comment on this month.  Still waiting for the work in NHS Lanarkshire to be scheduled in.

 

MVM104:

Strategy for the upgrade of our computer labs (annual)

 

Category Discretionary

 

Milestones
Target Date Title
31-Jul-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for March 2017

Achievements:
  • Meeting took place between Graham Newton, Lesley Greer and Alan Gilchrist to allow Graham to handover the master spreadsheet of the ISFM and MVMFM PCs.
  • The suggested replacement plan for MVMFM, which removes the large purchase spike in future years was discussed and this was then passed on to Paul Clark for budget agreement.  The initial plan for this year is to replace 124 PCs across MVM, however this figure may change by a few PCs depending on the use of rooms going forwards.  21 of the PCs are the Vets kiosk PCs which currently access the Tristan application, so funding for these still needs to be agreed.
  • Replacement PCs have started to be purchased, due to HP stating that they will be putting their prices up by 15% from Friday 7th April.

MVM105:

Strategy for upgrade of our teaching spaces (annual)

Category Discretionary

 

Milestones
Target Date Title
30-Jun-17 Closure
 
RAG Status

AMBER

Report by Alan Gilchrist for March 2017

Achievements:

Vet School:

AV contractor has been on-site to visit the rooms and is looking to schedule the work in for the first 3 weeks in June.  Most of the AV equipment will be built off-site.  Need to get Vet School to book out the rooms.

 

Chancellor's Building:

SU209 (PG Viva/Video Suite) - Engie has started work on redecorating the room and should be finished by the end of Friday 7th April.  Need to chase up the partition screen for this room and then procure the remaining AV kit.

Microlabs 1 & 2 - Engie stripped out the electrics to the centre desks on Wednesday 5th April.  All old chairs and desks were picked up by dirty works on the same day.  Work will carry on over April.

Undergraduate Medical Teaching Room - No progress on this room, so have set up a meeting with Estates and Engie to find out what the hold up is.  Concerns over this room, since it is booked out for the refurbishment in June and no minor works order has gone in to Engie yet.  AV tender will return on Friday 7th April.

Lecture Theatre A - AV tender will return on Friday 7th April.  No dates have been set for the refurbishment/upgrade yet.

 

Other rooms are on track as per previous reports.

MVM107:

Procurement of an online application to support assessment and feedback for MBChB

Category: Discretionary

 

Milestones
Target Date Title
31-Mar-17

Selection Complete

28-Apr-17 Aware Contract Milestone
26-May-17 Project Completion Milestone
 
RAG Status

GREEN

Report by Paul De'Ath for March 2017

Achievements this period
  • Procurement Consensus technical and finance complete
Issues
  • None caused an impact this month
Next Steps
  • Preparing to publish the recommendation paper
  • Then engage with the winning supplier, procurement and legal to create the contract
  • MVM119 ready to commence
  • MVM118 may be delayed until later in April before commencing
  • Both these projects continue the project initiated with MVM107

 

MVM111:

Technology to support short-notice communications to students

Category: Discretionary

 

Milestones
Target Date Title
31-Jul-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for March 2017

Achievements:
  • Several meetings have taken place to discuss options for the new academic year and whether MVM can be at the 'front of the queue' for the new notification service being released.
  • In the short term, it looks likely that MBChB will be able to make use of the LEARN announcements feature (since they are moving to LEARN over the summer) however the group structure within LEARN and processes for announcing items will need to be agreed by the academics.
  • Connecttxt is still an option for MBChB use, if they want to start using something in the very short term, however the admin overhead within the MTO, as well as the communications process and student opt-in form will still need to be agreed.

MVM115:

Technology to support TransNational Education (TNE)

Category: Discretionary

 

Milestones
Target Date Title
13-Apr-17  Project Brief signed off
18-Aug-17 Delivery complete
20-Oct-17 Complete closure report
 
RAG Status

GREEN

Report by Paul De'Ath for March 2017

Achievements this period
  • Project Brief approved by the Project Team
  • Commenced review and update to IT handbook
Issues
  • Prioritised activity on MVM107 reduced the Project Manager involvement this month
Next Steps
  • Project Brief to be approved by IS WIS
  • Continue work on IT Handbook

Category: Discretionary

MVM122:

Biomedical Sciences submission word count facility

Milestones
Target Date Title
TBC  
 
RAG Status

GREEN

Report by Alan Gilchrist for March 2017

Achievements:
  • Alan Gilchrist had some discussions with LTW (Myles Blaney) to see if there were certain features in existence which would negate the need for this project, however unfortunately at this point, none of the following can have a hard limit set for submissions, so an alternative solution will need to be found and implemented: TurnItIn Blackboard Moodle PebblePad
  • A Meeting with Karen Harris, Mayank Dutia, Sarfraz Mohammed, Jens Brincker and Alan Gilchrist took place on 7th March to discuss initial scope and requirements for the project.
  • Mayank showed the system he had been creating in Python which could be a possibility, however it was agreed that discussions would be initiated with the other Colleges to see if they had something implemented, as well as looking for off the shelf products which could be used.
  • Karen is looking for the solution to be implemented by mid-August, so that communication can go out to the students for the start of the new academic year.
  • A project manager still needs to be assigned to this, so for the time being it is sitting with Alan Gilchrist.

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
MVM024 Integration and adoption of ISFM This project started in 15/16 project, and was suspended in May 2016. This project was closed in January 2017. Any remaining activities will be completed as part of MVM120 Windows 10 rollout to computer labs within the Windows 10 Upgrade for Managed Desktops (W10).  
MVM032 Speedwell Service Implementation This project was closed on the 24 March 2017. The Completion Report is now available.