Report for April 2017

Report Date
April 2017
Report by Muriel Mewissen on behalf of Alan Gilchrist (MVMLAT Programme Managers)                             
for Sheila Lodge (MVMLAT Portfolio Owner)
and Paul Clark (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During April,  good progress was made. The main highlight is the award made to FRY-IT Practique following the evaluation process done as part of MVM107: Procurement of an online application to support assessment and feedback for MBChB. This project will carry on with the contract negotiation while new projects to deploy the software and migrate data to this new platform are initiated in the coming weeks.

One new project has started this month:

The overall status of the MVM Learning and Teaching programme is AMBER due to several projects being AMBER because of either delays or overspent:

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - April 2017

Section Two: Projects Not Started

Another 13 projects may start later this year, these are:

Project Programme Manager's Commentary
MVM102 Innovative Technology Review  
MVM103 Mobile Device Management  
MVM106 Student Print Strategy  
MVM108 Technology to support Attendance and Monitoring  
MVM109 Technology to support communications with potential students  
MVM110 Technology to support Open Educational Resources (OER)  
MVM112 Technology to support simulation teaching  
MVM113 Technology to support student portfolios  
MVM114 Technology to timetabling and room booking  
MVM116 Video Strategy  
MVM117 Virtual Desktop and software access  
MVM118: Deployment of an online application to support assessment and feedback for MBChB To start in May 2017
MVM121: Assessment and Feedback Reporting To start in April 2017

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

MVM101: Connectivity - on-campus and off-campus

Category: Discretionary

 

Milestones
Target Date Title
31-Jul-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for April 2017

Achievements this period
  • No progress has been made with NHS Lanarkshire.
Issues
  • Contractors have been trying to arrange dates with NHS IT staff but have so far been unsuccessful.
  • We have been informed by an academic that eduroam has been installed in NHS Forth Valley as part of an overhaul to their wireless network, however this hasn't been confirmed by the NHS IT staff yet.

 

MVM104:

Strategy for the upgrade of our computer labs (annual)

 

Category Discretionary

 

Milestones
Target Date Title
31-Jul-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for April 2017

Achievements this period
  • Most of the new MVMFM PCs have now been delivered and progress is as follows:
  • Chancellor's Building Library (47 PCs) - Installed
  • Chancellor's Building Seminar Rooms and Lecture Theatres (9PCs) - Installed
  • Kennedy Tower Computer Lab (8 PCs) - Delivered and waiting to be installed
  • Easter Bush HfSA F33 (8 PCs) - Delivered and waiting to be installed
  • Easter Bush Vet School Study Landscape (26 PCs) Delivered and waiting to be installed
Next Steps
  • Some of the Easter Bush Kiosk PCs will be funded by the College IT Learning and Teaching budget and the remainder will be funded by the Vet School (via Tim King).  These PCs haven't been purchased yet. 
  •  

MVM105:

Strategy for upgrade of our teaching spaces (annual)

Category Discretionary

 

Milestones
Target Date Title
30-Jun-17 Closure
 
RAG Status

AMBER

( Remaining at amber due to uncertainties with the installation dates of several of the rooms and a reliance on scheduling in external contractors. )

Report by Alan Gilchrist for April 2017

Vet School
  • Upgrades of the 7 rooms have been scheduled as follows:
  • Lecture Theatre 1 – Monday 12th and Tuesday 13th June (Friday 16th to clear up any issues)
  • Lecture Theatre 2 – Wednesday 14th and Thursday 15th June (Friday 16th to clear up any issues)
  • Seminar Room (G.01) – Thursday 22nd and Friday 23rd June
  • Rooms G.02 and G.02A – Friday 16th to Tuesday 20th June
  • Rooms G.03 and G.03A – Monday 29th May to Friday 2nd June (inclusive)

SMART podiums can no longer be obtained due to being discontinued by manufacturer, so an on-site demo of the Sharp LL-S201 interactive screen has been requested.

Requests for cabling works to be carried out have been passed to the local Estates team via the helpdesk system.

Chancellor's Building
Microlabs 1 and 2

These have had temporary furniture installed in order to get them back up and running for booked sessions to take place from Monday 8th May.  The rooms have been booked out again between 23rd May and 2nd June (morning) to allow permanent furniture to be installed.  It's critical the rooms are ready to be used again on the 2nd June as there are Infection Course Exams booked in from 1pm.  I'm still waiting for confirmation on when the new exam partition screens will be delivered.

Undergraduate Medical Teaching Room

Minor Works Orders have been sent in to engie and room has been booked out from 15th to 26th June and then again from 28th June to 25th July.  Engie will look to complete all of the decoration of the walls by the 26th June to allow a high stakes event to take place on the 27th.  The remaining redecoration will then start again on the 28th June.  I'm waiting for specific dates from the AV contractor as to when they can start their work.

Board Room

Minor Works Order has been approved and dates are being looked at for work to commence.  The AV contractor has been appointed and I'm waiting for dates as to when they will be available.

SU209

Redecoration work has been completed and AV contractor should be on site during week beginning 8th May (subject to completing RAMS documentation).  I'm still waiting for confirmation on when the furniture and partition screen will be delivered.

Lecture Theatre A

Minor Works Orders have been sent to engie and am waiting to hear back regarding costs.  Scheduling dates for the work to be carried out is proving difficult due to numerous bookings within the room (some of which I've been told can't be moved).  AV contractor has been appointed and will come on-site during May to look at existing configuration and plane new work.

MVM107:

Procurement of an online application to support assessment and feedback for MBChB

Category: Discretionary

 

Milestones
Target Date Title
05-May-17 Award Contract Milestone
26-May-17 Project Completion Milestone
 
RAG Status

AMBER

(Budget overspent)

Report by Paul De'Ath for April 2017

Achievements this period
  • Legal and Procurement have created a new SaaS contract and are proceeding with FRY-IT
Issues
  • The signing of the contract is taking longer than anticipated, though no issue has been reported
Next Steps
  • Writing the lessons learnt and closure report

MVM111:

Technology to support short-notice communications to students

Category: Discretionary

 

Milestones
Target Date Title
31-Jul-17 Closure
 
RAG Status

GREEN

Report by Alan Gilchrist for April 2017

Achievements this period

Have not been told to progress any work with the ConnecTxt service, so no updates to provide on this project this month.

MVM115:

Technology to support TransNational Education (TNE)

Category: Discretionary

 

Milestones
Target Date Title
26-May-17 2016 Tag change - all work complete
26-Jun-17 All Biomedical Teaching Organisation input received as of end of May 2017 - IT Handbook updated
18-Aug-17 Delivery complete
20-Oct-17 Complete closure report
 
RAG Status

AMBER

(Budget overspent due to earlier work associated to MVM115)

Report by Paul De'Ath for April 2017

Achievements this period
  • The Project Brief was approved at the IS WIS
Issues
Next Steps
  • Continue the new draft version of the IT Handbook
  • Obtain and insert material from Kate and Hugh - covering year 1 manual activity, lessons learned and full documentation of fix and testing

MVM119

Data Migration and Data Creation for the online assessment and feedback application for MBChB

Category: Discretionary

 

Milestones

Target Date Title
19-May-2017 Present Project Brief to IS WIS
30-Jun-2017 Mock Exam content ready to run
29-Sep-2017 Year 6 Formative Exam ready
30-Nov-2017 Year 5 Summative Exam ready
21-Dec-2017 Recommendation report created
31-Jan-2018 Close report created
 
RAG Status

GREEN

Report by Paul De'Ath for April 2017

Achievements this period
  • The Project initiation was approved at the IS WIS on April 14
  • FRY-IT have supplied the data import template for the first exam from OSCA+ that has been identified to be migrated
  • LTW development confirm they will commence the initial extract in the first week of May
Issues
Next Steps
  • LTW Dev will produce the first data extract according to the suppliers, FRY-IT, template
  • PM meeting with FRY-IT on the week commencing May 1st to run through the high level plan - will include MVM118 (which will be initiated in the first week of May)
 

MVM122:

Biomedical Sciences submission word count facility

Category: Discretionary

 

Milestones
Target Date Title
TBC  
 
RAG Status

AMBER

(Concern over timescale)

Report by Alan Gilchrist for April 2017

Achievements

Emails were sent to Frasier Muir (CAHSS) and Colin Higgs (CSE) to check if either College has implemented a similar solution, however both replied stating they don't have hard limits automatically set for their student submissions.  The next steps are therefore to scope what's available either via open source or commercial applications and compare them to the possible solution built by Mayank in Biomedical Sciences.

Issues
  • Karen Harris is getting concerned with the timescale of this project, as workbooks will need to be amended over the summer in preparation for the new academic year.
  • A project manager still hasn't been appointed to this, so remains with Alan Gilchrist at the moment.

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
MVM024 Integration and adoption of ISFM This project started in 15/16 project, and was suspended in May 2016. This project was closed in January 2017. Any remaining activities will be completed as part of MVM120 Windows 10 rollout to computer labs within the Windows 10 Upgrade for Managed Desktops (W10).  
MVM032 Speedwell Service Implementation This project was closed on the 24 March 2017. The Completion Report is now available.

Programme Info