Report for February 2020

Report Date
February 2020

 

Report by Susan Ridder-Patrick (MVMLAT Programme Manager) for Philippa Burrell (MVMLAT Programme Owner) and Catherine Elliot (MVM Portfolio Owner)

Distribution:

  • Vet and Medical School sub-group IT meeting
  • College Administration Team (CAT) meeting
  • College Undergraduate Learning and Teaching (CULT) committee
  • Post Graduate Learning and Teaching (PGLTC) committee
  • Excerpts taken into CSG report

Section One: Programme Commentary, RAG and Resources Update

Commentary

Programme status: The overall status of the MVMLAT programme is GREEN. There is some impact from industrial action but the prioritisation for 19/20 has been completed and most projects are progressing to plan.

Risks

  • Industrial action: This risk has increased - the programme's work is being impacted again from planned industrial action in February and March 2020.
  • Novel Coronavirus (Covid-19): There is a risk this programme may be impacted by any measures that are implemented to reduce impact from the spread of Covid-19. The risk is held at portfolio level.

Project highlights

  • MVM112: First half of draft report for simulation equipment has been completed, which has identified specific years when replacement costs are due to be incurred.
  • MVM125: The second PC for the PAEP library has been built and configured to use a mobile broadband USB dongle
  • MVM132: Second draft of report with lead for testing. Location of report agreed.
  • MVM134: Development work delivered. Project now moving into Closure.
  • MVM135: New proposed layout for the Greenfield Suite main lab is confirmed
  • MVM136: Training days took place as planned on 24/25 February. Vets/BMTO LIVE and TEST instances delivered and Single sign-on implemented 
  • MVM137: Discussed replacements with local IT teams, identifying possible storage options for the deliveries. Delivery from HP may be delayed due to impact to manufacturing from Covid-19.
  • MVM138: Some impact from MVM134 overrun but efficiencies were possible reusing some of the development from MVM134.
  • MVM139: Technical upgrade completed. Project now in planned suspension until other projects have delivered and resources are available.
  • MVM516: Project has started but has been impacted by industrial action.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - February 2020  

 

Section Two: Projects Not Started 

Due to competing priorities and lack of capacity in MVM, there are a number of projects noted as not currently planned for inclusion in 19/20.

Project Programme Manager's Commentary
House Hub Start date TBC 
Labyrinth TBC - not currently planned in 19/20
PathCAL TBC - not currently planned in 19/20
MVM102 Innovative Technology review TBC - not currently planned in 19/20
MVM106: Student Print Strategy TBC if still required - not currently planned in 19/20
MVM109 Technology to support communications with potential students. TBC if covered by SEP SRA Enquiry Management - not currently planned in 19/20
MVM110 Technology to support Open Educational Resources (OER) TBC - not currently planned in 19/20
MVM113 Technology to support student portfolios TBC if still required - not currently planned in 19/20

 

Section Three: Projects in Progress

MVM Learning and Teaching Projects Update

MVM112: Technology to support simulation teaching - RAG Status: GREEN

Report by Alan Gilchrist 

Achievements this period

  • First half of draft report for simulation equipment has been completed, which has identified specific years when replacement costs are due to be incurred.
  • Briefly reviewed database information provided by other organisation.  To progress any further with this route requires GDPR checks.

Issues

  • None

Next Steps

  • Evaluate the possibility of another organisation's database to see if it could be used within our context.
  • Continue development of Simulated Patient database, looking more into the MS PowerApps route.
  • Complete second half of draft report outlining the University’s simulation equipment currently available within the Chancellor’s Building Clinical Skills Centre and WGH MEC.  Include proposed maintenance costs, annual recurring costs and replacement cycles.

MVM125: Connectivity - Off-campus 2018/19 - RAG Status: GREEN

Report by Alan Gilchrist  

Achievements this period

  • The second PC for the PAEP library has been built and configured to use a mobile broadband USB dongle.

Issues

  • Requests for additional wireless networking resource in the student residences at the Borders General Hospital have been received by the ACT officer.  The residences are currently provided with a shared BT Infinity connection, however this doesn't appear to be giving sufficient bandwidth for the number of students.  Options for improvement would be either to see if the NHS would extend their wireless network out to the residences (unlikely based on past experience) or to increase the number of BT connections to the residences.  Given funding constraints this year, can the College provide money to improve the student's wi-fi experience next financial year?

Next Steps

  • Deliver two PCs to the PAEP library for student use.
  • Create easy rebuild procedure for PAEP library, since it is not a fully supported desktop build.
  • Receive suggested options for restoring eduroam connectivity in NHS Lanarkshire.
MVM132 MBChB ranking reports in BI Suite  - RAG Status: GREEN
Report by Susan Ridder-Patrick

Achievements this period

  • Second draft of the report was supplied to Business Lead as planned on 14th February.
  • Location of report agreed

Issues

  • None

Next Steps

  • Completion of re-testing (starting after 17th March)
  • Re-work and re-testing if required
  • Confirmation of second report owner in MVM
  • Closure

MVM134 MBChB Evaluation System - RAG Status: GREEN

Report by Andrew Millington 

Achievements this period

  • Fixed tutor evaluation system
  • Implemented search which was missing from original workload
  • Added NPI scores and updated question scores to comply with old system

Issues

  • None

Next Steps

  • Seek formal sign-off for closure of project

MVM135 Upgrading of Teaching Spaces 2019/20 - RAG Status: GREEN

Report by Alan Gilchrist 

Achievements this period

  • New proposed layout for the Greenfield Suite main lab is confirmed, based on the feedback provided by the main users of the space.  Designs have been created and discussions with estates have begun.
  • Rooms identified for this year are now being split between two budgets, which has provided us with additional funding to cover most of the rooms we have identified for this year.
  • AV designs for all of the Vet School rooms (other than room 1.21 Clinical Skills) have been completed.

Issues

  • Ceiling height in the Greenfield Suite side rooms is an issue for installing the Nureva Span/Wall system proposed, based on the information given on Nureva's website.  Need to identify possible alternative if this can't be resolved.

Next Steps

  • Further investigation regarding the equipment requirements for Vet School 1.21 Clinical Skills needs to be carried out.
  • Discussion with Nureva regarding limited ceiling height is scheduled for March 10th.
  • Complete remaining AV designs and then tender documents for each of the room upgrades.

MVM136 Practique Roll-out - RAG Status: GREEN

Report by Susan Ridder-Patrick

Achievements this period

  • Training days completed for Vets and BMTO
  • SSO enabled on TEST and LIVE Vets/BMTO instances

Issues

  • None

Next Steps

  • Supplier to provide report from training days
  • Vets to prepare for pilot
  • BMTO to consider actions from training day for EMQs

MVM137 Upgrading of Student Computer Labs , Teaching and Meeting Room PC 19/20 - RAG Status: GREEN

Report by Alan Gilchrist  

Achievements this period

  • Discussed replacements with local IT teams, identifying possible storage options for the deliveries.

Issues

  • Delivery estimates from HP are very vague at the moment due to uncertainties regarding manufacturing.  These estimates vary at the moment, with possible cases being 3 months or more.

Next Steps

  • Create orders for the PC replacements in March.  Depending on delivery times (if shorter than expected) PCs for the Vet School may have to be delivered to our offsite storage provider.

MVM516 BMS - Honours Project Portal Future Support - RAG Status: AMBER

Report by Susan Ridder-Patrick

Achievements this period

  • Code has been downloaded and initial work has started but no tasks have been completed ye

Issues

  • Development delayed due to industrial action and competing projects within the development team

Next Steps

  • Commence development of project

MVM138 Vets EMS Placement Management - RAG Status: GREEN

Report by Andrew Millington

Achievements this period

  • Ability to add/edit/delete clinical EMS practices
  • Ability to search for clinical EMS practices
  • Ability to add/edit/delete vets in the system
  • View detailed search results about placement providers

Issues

  • Had not estimated time to switch between animal husbandry and clinical contexts for students and admins. This was added into the system but took some time to implement
  • Automatic tests are sometimes failing. Team will take some time this week to investigate this issue to ensure tests work as expected
  • Some development time was lost as MVM134 development had not finished and required some development time

Next Steps

  • Continue development, focussing on admin functionality so we can lay the groundwork for student placements

MVM139 Curriculum Mapping Tool (COMMAND) RAG Status: SUSPENDED (BLUE)

Report by Andrew Millington

Achievements this period

  • Deployed Com-mand running on PHP 7.3 to production

Issues

  • None

Next Steps

  • None. Project on hold until later in the year when the team has available resources to work on this

Projects outwith the MVM Portfolio Update

Report by Alan Gilchrist and Karen Howie (LTW):

EEMeC and EEVeC

The programme has been and continues to complete projects to close down functionality on both EEMeC and EEVeC with a view to eventually decommissioning.  There is a requirement to maintain (read only) access for a period and the programme is in the process of determining those dates for its 3 year plan.

 

TEL056: Edinburgh Surgery Online Learn go-live - RAG Status: BLUE - Closed

DTP001: Apps to User Devices - RAG Status: GREEN

Summary of Achievements in last period:

  • Progress on actions 
  • Technical issue affecting Apps Ed now resolved enabling delivery of Soft Launch
  • Soft launch completed as scheduled - 3rd February 2020
  • MVM students moved from old service
  • Old service decommissioned

Risks and Issues

  • No new issues raised

Next Steps 

  • Project activity stand still period to gather and analyse feedback from Soft Launch
  • Schedule communications for go live
  • Schedule Project Board meeting for post-soft launch
  • Schedule closure activities
  • Attain approval for project closure

HSS022: CAHSS WAM Deployment  - RAG Status: BLUE - Closed

TEL057: Learn Foundations - RAG Status: GREEN

Achievements this period

  • Continued on the Phase Two work streams.
  • Continued with the 2nd round of engagement sessions with the non-phase one Schools.
  • Continued to gain commitment from the non-phase one Schools to join the Learn Foundations project within Phase Two.
  • UX recruitment and activity continued.
  • Phase Two review of the programme of training continued.
  • Raised awareness of the project within CAHSS by attending the UG Directors Committee

Issues

  • As with November, industrial action has impacted the progress of the project with various stakeholders being away from the office before moving into the Christmas and New Year period where no UX activity could be scheduled. 
  • New industrial action is currently in progress and as such, there has been an impact to the project within February and March.  All plans have been reviewed as a result

Next Steps

  • Continue on the Phase Two work streams.
  • Complete the 2nd round of engagement sessions with the non-phase one Schools.
  • Gain commitment from the non-phase one Schools to join the Learn Foundations project within Phase Two.
  • UX recruitment and activity to be continued.
  • Phase Two review of the programme of training to be continued.

Section Four: Closed or Withdrawn Projects

Only those projects closed from 28th June 2019 onwards are included in this table. A full history of completed projects is available on the programme's website.

Project Info Project Manager's Commentary
MVM126 Upgrading of student computer labs, teaching and meeting room PCs 2018/19 This project started in October 2018 and closed on 28 June 2019. The Closure report is now available.
MVM129 Support for OSCEs in Practique for MBChB This project started in June 2018 and closed on 28 June 2019. The Closure Report is now available.
MVM131: Migration of 12 applications developed in Biomedical Sciences to central support - Analysis & Strategy This project started in December 2018 and closed on 28 June 2019. The Closure Report is available to view.
MVM133: CMVM Curriculum Mapping Tool - Requirements This project started in April 2019 and closed on 9th August 2019.  The Closure Report is available to view. 
MVM130: Upgrading of teaching spaces 2018/19 This project started in October 2018 and closed on 1st November 2019. The Closure Report is available to view.

Section Five: Programme Meeting Minutes

Minutes for all programme meetings are available on the MVMLAT website. Only the most recent five meetings direct links are included in this table:

Date

Comments

18 February 2020 Programme Review Monthly Meeting - January 2020
14 January 2020 Programme Review Monthly Meeting - December 2019
10 December 2019 Programme Review Monthly Meeting - November 2019
12 November 2019 Programme Review Monthly Meeting - October 2019
22 October 2019 Programme Review Monthly Meeting - September 2019
9 September 2019 Programme Review Monthly Meeting - August 2019

Section Six: MVM Portfolio Projects Update 

The MVM Portfolio contains three programmes: CMVM Learning and Teaching - MVMLAT (this programme); CMVM Business Administration - MVMBUS and CMVM Research - MVMRES. Information on current work in MVMBUS and MVMRES are available on the following websites:

AttachmentSize
Image icon forward_look_feb_20.png63.41 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No