Report for August 2020
- Report Date
- August 2020
Report by Susan Ridder-Patrick (MVMLAT Programme Manager) for Philippa Burrell (MVMLAT Programme Owner) and Catherine Elliot (MVM Portfolio Owner)
Distribution:
-
Vet and Medical School sub-group IT meeting
-
College Administration Team (CAT) meeting
-
College Undergraduate Learning and Teaching (CULT) committee
-
Post Graduate Learning and Teaching (PGLTC) committee
-
Excerpts taken into CSG report
Section One: Programme Commentary, RAG and Resources Update
Commentary
Programme status: The overall status of the MVMLAT programme for August 2020 is AMBER. The CMVM eAssessment project delivered as planned and progress was made on the majority of other projects. However, further slight delays in Vets EMS (MVM138) and BMS Hons Portal (MVM516) projects continue to put the development and delivery of the 20/21 plan at risk.
Risks
- Novel Coronavirus (Covid-19): There is a risk this programme may be impacted by any measures that are implemented to reduce impact from the spread of Covid-19. The risk is held at portfolio level.
Project highlights
- MVM112: GREEN - Simulated Patient database development completed; project now in Closure phase
- MVM125: SUSPENDED
- MVM135: AMBER - Progress has been made on some installations but delay in some deliveries and error in another putting project at risk
- MVM136: GREEN - no project progress this month as priority was programme work to secure contract for 20/21. Overall project timelines unaffected.
- MVM138: AMBER - Progress made but slight delay to deployment
- MVM139: SUSPENDED
- MVM140: GREEN - Delivered in August as planned. Closure process underway.
- MVM516: AMBER - Progress this month means project's status decreased to AMBER from RED last month.
Non-project work
- Security issue on open.med: Solution has been deployed
- Contract renewal process for Practique for academic year 20/21 completed
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Forward Look - August 2020
Section Two: Projects Not Started
Project | Programme Manager's Commentary |
---|---|
House Hub | TBC - not currently planned in 19/20; may be able to use software already available |
Labyrinth | In draft plan for 20/21 |
PathCAL | In draft plan for 20/21 |
Section Three: Projects in Progress
MVM Learning and Teaching Projects Update
MVM112: Technology to support simulation teaching - RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM125: Connectivity - Off-campus 2018/19 - RAG Status: SUSPENDED Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM135 Upgrading of Teaching Spaces 2019/20 - RAG Status: AMBER Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM136 Practique Roll-out - RAG Status: GREEN Report by Susan Ridder-PatrickAchievements this period
Issues
Next Steps
|
|
MVM516 BMS - Honours Project Portal Future Support - RAG Status: AMBER Report by Andrew MillingtonAchievements this period
Issues
Next Steps
|
|
MVM138 Vets EMS Placement Management - RAG Status: AMBER Report by Andrew MillingtonAchievements this period
Issues
Next Steps
|
|
MVM139 Curriculum Mapping Tool (COMMAND) RAG Status: SUSPENDED Report by Andrew MillingtonAchievements this period
Issues
Next Steps
|
|
MVM140 CMVM eAssessment RAG Status: GREEN Report by Alistair WallaceAchievements this period
Issues
Next Steps
|
Projects outwith the MVM Portfolio Update
Report by Alan Gilchrist and Karen Howie (LTW):
EEMeC and EEVeC The programme has been and continues to complete projects to close down functionality on both EEMeC and EEVeC with a view to eventually decommissioning. There is a requirement to maintain (read only) access for a period and the programme is in the process of determining those dates for its 3 year plan.
|
|
TEL056: Edinburgh Surgery Online Learn go-live - RAG Status: CLOSED
|
|
DTP001: Apps to User Devices - RAG Status: CLOSED
|
|
HSS022: CAHSS WAM Deployment - RAG Status: BLUE - Closed
|
|
TEL057: Learn Foundations - RAG Status: GREEN The Learn Foundations focus is primarily on the support being delivered by our student interns in preparation for teaching in Semester 1. The below provides an overview of the work completed to date: Core 20 interns CAHSS Learn Foundations has been working with 9 of the CAHSS Schools to become partners and adopt the Learn Foundations template. The following provides an overview on the Learn Foundations template adoption within CAHSS:
CSE Learn Foundations are working with all CSE Schools to drive 100% adoption for Semester 1. The following provides an overview on the Learn Foundations template adoption within CSE:
CMVM Learn Foundations are working with 4 of the Schools/Deaneries within the College to become partners and adopt the Learn Foundations template. The following provides an overview on the Learn Foundations template adoption within CMVM:
In Progress: For those Schools which are ‘In Progress’ (ECA and LLC), we have adopted a different model to provide additional support for both Schools in the migration of their content (course materials) onto the new Learn Foundations template. Completed with the exception of courses in query: All migration work has been completed with the exception of any courses which could not be assigned on Learn. These have been/are being investigated and fed back to the School for guidance. In the majority of cases these are due to changes being made to course delivery after the original data set was received (i.e. Semester change etc.). Additional Support With the majority of the core migration work completed, we are now looking at how we support Schools in their preparations for their hybrid approach. We are working with/in conversation with our partner Schools to look at how we can continue to provide support in preparation for Semester 1 with focus being on:
The following Schools have taken up our offer of additional support/we are in discussions to uptake this offer of support:
All remaining Schools are in the process of having next step discussions are ongoing. Several of our interns ended their internship on the 21st August 2020; however, due to the preparation requirements for Semester 1, we have extended 20 interns for an additional 4 weeks. These interns will continue to support our partner Schools in their Semester 1 preparations until 18th September 2020. |
Section Four: Closed or Withdrawn Projects
Only those projects closed from 28th June 2019 onwards are included in this table. A full history of completed projects is available on the programme's website.
Project Info | Project Manager's Commentary |
---|---|
MVM126 Upgrading of student computer labs, teaching and meeting room PCs 2018/19 | This project started in October 2018 and closed on 28 June 2019. The Closure report is now available. |
MVM129 Support for OSCEs in Practique for MBChB | This project started in June 2018 and closed on 28 June 2019. The Closure Report is now available. |
MVM131: Migration of 12 applications developed in Biomedical Sciences to central support - Analysis & Strategy | This project started in December 2018 and closed on 28 June 2019. The Closure Report is available to view. |
MVM133: CMVM Curriculum Mapping Tool - Requirements | This project started in April 2019 and closed on 9th August 2019. The Closure Report is available to view. |
MVM130: Upgrading of teaching spaces 2018/19 | This project started in October 2018 and closed on 1st November 2019. The Closure Report is available to view. |
MVM134 MBChB Evaluation System | This project started in September 2019 and closed on 8th April 2020. The Closure Report is available to view. |
MVM137 Upgrading of Student Computer Labs , Teaching and Meeting Room PC 19/20 | This project started in December 2019 and closed on 6th July 2020. The Closure report is available to view. |
MVM132 MBChB ranking reports in BI Suite | This project started in April 2019 and closed on 31 July 2020. The Closure report is available to view. |
Section Five: Programme Meeting Minutes
Minutes for all programme meetings are available on the MVMLAT website. Only the most recent five meetings direct links are included in this table:
Date |
Comments |
---|---|
10 August 2020 | Programme Review Monthly Meeting - July 2020 |
16 July 2020 | Programme Review Monthly Meeting - June 2020 |
19 June 2020 | Programme Review Monthly Meeting - May 2020 |
14 May 2020 | Programme Review Monthly Meeting - April 2020 |
21 April 2020 | Programme Review Monthly Meeting - March 2020 |
Section Six: MVM Portfolio Projects Update
The MVM Portfolio contains three programmes: CMVM Learning and Teaching - MVMLAT (this programme); CMVM Business Administration - MVMBUS and CMVM Research - MVMRES. Information on current work in MVMBUS and MVMRES are available on the following websites:
Attachment | Size |
---|---|
mvmlat_fl_aug_20.png | 49.8 KB |