Report for October 2020
- Report Date
- October 2020
Report by Susan Ridder-Patrick (MVMLAT Programme Manager) for Philippa Burrell (MVMLAT Programme Owner) and Catherine Elliot (MVM Portfolio Owner)
Distribution:
-
Vet and Medical School sub-group IT meeting
-
College Administration Team (CAT) meeting
-
College Undergraduate Learning and Teaching (CULT) committee
-
Post Graduate Learning and Teaching (PGLTC) committee
-
Excerpts taken into CSG report
Section One: Programme Commentary, RAG and Resources Update
Commentary
Programme status: The overall status of the MVMLAT programme for October 2020 is AMBER. The BMS Honours Portal project has now closed following delivery last month. Several projects are encountering delays due to challenges in availability of key staff.
Risks
- Novel Coronavirus (Covid-19): There is a risk this programme may be impacted by any measures that are implemented to reduce impact from the spread of Covid-19. The risk is held at portfolio level.
Project highlights
- MVM125: AMBER - Project came out of suspension in October and is now addressing multiple issues
- MVM136: GREEN - Admissions Assessment for 2020/21 has been brought into the scope of the project
- MVM139: AMBER - Challenges getting time with key College staff to test and approve development
- MVM140: AMBER - Project extended slightly to agree Service operations/processes
- MVM141: AMBER - planning milestone has been rescheduled to enable clarity on scope and deliverables; initial analysis underway
- MVM142: GREEN - Brief drafted for review; Set PCs to be only able to be used from Monday to Friday 9am - 5pm (MEC) and equivalent for other study spaces
- MVM143: GREEN - Upgrading of Teaching Spaces project has been initiated for 20/21
- MVM144: GREEN - Upgrading of student computer labs, teaching and meeting room PCs project has been initiated for 20/21
- MVM516: CLOSED - This project has now closed following delivery at the start of October
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Forward Look - October 2020
Section Two: Projects Not Started
Project | Programme Manager's Commentary |
---|---|
House Hub | TBC - not currently planned in 20/21; may be able to use software already available |
Section Three: Projects in Progress
MVM Learning and Teaching Projects Update
MVM125: Connectivity - Off-campus 2018/19 - RAG Status: AMBER Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM136 Practique Roll-out - RAG Status: GREEN Report by Susan Ridder-PatrickAchievements this period
Issues
Next Steps
|
|
MVM139 Curriculum Mapping Tool (COMMAND) RAG Status: AMBER Report by Arek JuszczykAchievements this period
Issues
Next Steps
|
|
MVM140 CMVM eAssessment RAG Status: AMBER Report by Alistair WallaceAchievements this period
Issues
Next Steps
|
|
MVM141 Replacement for PathCAL/EROS and Labyrinth RAG Status: AMBER Report by Susan Ridder-PatrickAchievements this period
Issues
Next Steps
|
|
MVM142 CMVM Study Spaces RAG Status: GREEN Report by Sheila FraserAchievements this period
Issues
Next Steps
|
|
MVM143 Upgrading of Teaching Spaces 2020/21 RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
|
MVM144 Upgrading of student computer labs, teaching and meeting room PCs 2020/21 RAG Status: GREEN Report by Alan GilchristAchievements this period
Issues
Next Steps
|
Projects outwith the MVM Portfolio Update
Report by Alan Gilchrist and Karen Howie (LTW):
EEMeC and EEVeC The programme has been and continues to complete projects to close down functionality on both EEMeC and EEVeC with a view to eventually decommissioning. There is a requirement to maintain (read only) access for a period and the programme is in the process of determining those dates for its 3 year plan.
|
|
TEL056: Edinburgh Surgery Online Learn go-live - RAG Status: CLOSED
|
|
DTP001: Apps to User Devices - RAG Status: CLOSED
|
|
HSS022: CAHSS WAM Deployment - RAG Status: BLUE - Closed
|
|
TEL057: Learn Foundations - RAG Status: GREEN Achievements in the last period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Only those projects closed from 28th June 2019 onwards are included in this table. A full history of completed projects is available on the programme's website.
Project Info | Project Manager's Commentary |
---|---|
MVM126 Upgrading of student computer labs, teaching and meeting room PCs 2018/19 | This project started in October 2018 and closed on 28 June 2019. The Closure report is now available. |
MVM129 Support for OSCEs in Practique for MBChB | This project started in June 2018 and closed on 28 June 2019. The Closure Report is now available. |
MVM131: Migration of 12 applications developed in Biomedical Sciences to central support - Analysis & Strategy | This project started in December 2018 and closed on 28 June 2019. The Closure Report is available to view. |
MVM133: CMVM Curriculum Mapping Tool - Requirements | This project started in April 2019 and closed on 9th August 2019. The Closure Report is available to view. |
MVM130: Upgrading of teaching spaces 2018/19 | This project started in October 2018 and closed on 1st November 2019. The Closure Report is available to view. |
MVM134 MBChB Evaluation System | This project started in September 2019 and closed on 8th April 2020. The Closure Report is available to view. |
MVM137 Upgrading of Student Computer Labs , Teaching and Meeting Room PC 19/20 | This project started in December 2019 and closed on 6th July 2020. The Closure report is available to view. |
MVM132 MBChB ranking reports in BI Suite | This project started in April 2019 and closed on 31 July 2020. The Closure report is available to view. |
MVM138 Vets EMS Placement Management | This project started in January 2020 and closed on 29 September 2020. The Closure Report is available to view. |
MVM112 Technology to support simulation teaching | This project started in September 2017 and closed on 30 September 2020. The Closure Report is available to view. |
MVM135 Upgrading of Teaching Spaces 2019/20 | This project started in December 2019 and closed on 30 September 2020. The Closure Report is available to view. |
MVM516 BMS - Honours Project Portal Future Support | This project started in May 2019 and closed on 19 October 2020. The Closure Report is available to view. |
Section Five: Programme Meeting Minutes
Minutes for all programme meetings are available on the MVMLAT website. Only the most recent five meetings' direct links are included in this table:
Date |
Comments |
---|---|
13 October 2020 | Programme Review Monthly Meeting - September 2020 |
7 September 2020 | Programme Review Monthly Meeting - August 2020 |
10 August 2020 | Programme Review Monthly Meeting - July 2020 |
16 July 2020 | Programme Review Monthly Meeting - June 2020 |
19 June 2020 | Programme Review Monthly Meeting - May 2020 |
Section Six: MVM Portfolio Projects Update
The MVM Portfolio contains three programmes: CMVM Learning and Teaching - MVMLAT (this programme); CMVM Business Administration - MVMBUS and CMVM Research - MVMRES. Information on current work in MVMBUS and MVMRES are available on the following websites: