Report for November 2020

Report Date
November 2020

 

Report by Susan Ridder-Patrick (MVMLAT Programme Manager) for Philippa Burrell (MVMLAT Programme Owner) and Catherine Elliot (MVM Portfolio Owner)

Distribution:

  • Vet and Medical School sub-group IT meeting
  • College Administration Team (CAT) meeting
  • College Undergraduate Learning and Teaching (CULT) committee
  • Post Graduate Learning and Teaching (PGLTC) committee
  • Excerpts taken into CSG report

Section One: Programme Commentary, RAG and Resources Update

Commentary

Programme status: The overall status of the MVMLAT programme for November 2020 is AMBER. Availability/capacity for all staff groups involved is impacting progress on some projects.

Risks

  • Novel Coronavirus (Covid-19): There is a risk this programme may be impacted by any measures that are implemented to reduce impact from the spread of Covid-19. The risk is held at portfolio level.

Project highlights

  • MVM125: AMBER - ongoing issues across multiple locations
  • MVM136: GREEN - Digital Admissions Assessment days organisation progressed. BMTO and Admissions Assessment not using Practique for any further work in 20/21. 
  • MVM139: AMBER - Progress was made following session with key MVM staff but revised delivery date will be required
  • MVM140: AMBER - Further delay in getting Service operations/processes agreed. Now expected mid-January 2021
  • MVM141: AMBER - Some progress to identify content using Flash and owners of some content in Labyrinth and PathCAL. No progress on project brief due to conflict on Project Manager's time.
  • MVM142: GREEN - Brief approved and agreement for Dentistry to move to SeatED
  • MVM143: GREEN - Project progressing to plan
  • MVM144: GREEN - No progress this month but no impact to overall planned delivery

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - November 2020

Section Two: Projects Not Started 

 

Project Programme Manager's Commentary
House Hub TBC - not currently planned in 20/21; may be able to use software already available

 

Section Three: Projects in Progress

MVM Learning and Teaching Projects Update

MVM125: Connectivity - Off-campus 2018/19 - RAG Status: AMBER

Report by Alan Gilchrist  

Achievements this period

  • NHS Lothian IT have confirmed (with screenshots) that Blackboard Collaborate works fine on their network, so long as NHS staff are using a Windows 10 based device (which has the latest version of Chrome installed).  They have provided details on what staff should do if their computer hasn't been upgraded to Windows 10, or if they don't have the necessary peripherals (i.e. webcam or headset).

Issues

  • Ongoing issues with the purchasing of SIM cards for tablets to go out to NHS sites.  MVM procurement are discussing the paperwork requirements with central finance.
  • The USB mobile broadband dongles for student use in NHS Lanarkshire only work on Windows based devices or Apple Macs prior to OS X Catalina (they require 32-bit support) so these will need to be upgraded.
  • NHS Lanarkshire are still experiencing issues with their eduroam wifi.

Next Steps

  • Upgrade the wifi dongles for NHS Lanarkshire.
  • Contact NHS Lanarkshire IT to discuss issues with their eduroam connectivity.
  • Contact NHS Borders to decide the best route for investigating issues in the student residences.
  • Complete the financial processes in order to procure the new SIM cards for tablets, so that they can be delivered to numerous NHS sites.

MVM136 Practique Roll-out - RAG Status: GREEN

Report by Susan Ridder-Patrick

Achievements this period

  • Admissions team have confirmed that they will use Collaborate for all the video-conferencing in the Assessment days
  • Admissions team have confirmed that the assessors will not be using Practique this year due to need to reduce risk when completing remotely. The Admissions Assessments will not be de-scoped from the project as the PM is providing support to the Assessments team (supplier, headsets, circuit managers)
  • Headsets loaned from Clearing team to Admissions team for those few applicants who may need to attend on site (eg insufficient technology at home) and for any assessors that are on-site.
  • BMTO have confirmed that they have sufficiently piloted Practique to understand the product and will not run further exams in 20/21. This will enable the BMTO team to focus effort in 20/21 on TEL068

Issues

Next Steps

  • Change control for scope to be processed
  • Complete Circuit Manager recruitment

MVM139 Curriculum Mapping Tool (COMMAND) RAG Status: AMBER

Report by Arek Juszczyk

Achievements this period

  • Work on UI improvement started
  • Institutions functionality removed
  • Functionality to manage curriculum status and publishing
  • Updated home page 
  • Bug fixes

Issues

  • User Interface upgrade work stopped as not top priority

Next Steps

  • Outcomes editing workflow
  • Preview mapping as Student

MVM140 CMVM eAssessment RAG Status: AMBER

Report by Alistair Wallace

Achievements this period

  • None

Issues

  • It became clear that the existing operational processes in BAU were not as effective as the business wanted.  A practical example with non UoE staff's names not feeding through evidenced that additional support was required in this area.  It has taken longer than anticipated to discuss and agree the operational processes required in BAU.  The business recommended the revision to the target date and the exercise to agree changes to processes continues with a target date of 15th January.
  • Problems have been identified with the data download associated with reporting from Pebblepad.  While filtering can take place within the app, the download contains all the data and therefore is substantial and requires manual effort.  Investigation is taking place into the use of Power BI to assist and Pebblepad are being approached to identify if the download can be more easily managed.  A meeting has taken place with Pebblepad although the solution proposed by them has been rejected by the Business.  The business has built a Power BI report that meets their needs however the overhead to format the data to be used is still significant.

Next Steps

  • Approval of Change to "Service operations/processes agreed" milestone

MVM141 Replacement for PathCAL/EROS and Labyrinth RAG Status: AMBER

Report by Susan Ridder-Patrick

Achievements this period

  • Further analysis of content and content owners for Labyrinth and PathCAL
  • Discussion about Xerte with CAHSS 

Issues

  • PM was unable to complete brief due to lack of capacity 

Next Steps

  • Revise planning milestone
  • Complete project brief
  • Begin replacement of Flash content by priority of need for semester 2

MVM142 CMVM Study Spaces RAG Status: GREEN

Report by Sheila Fraser

Achievements this period

  • Reviewed Dentistry study spaces temporary MS Booking solution. Agreed that the SeatEd app would be a suitable replacement, with an initial target date for move in January 2021.
  • Project brief approved

Issues

  • None

Next Steps

  • Move Dentistry to SeatEd App and decommission existing MS Booking solution, target of January (will depend on workload of facilities team supporting testing).
  • Evaluate remaining PC spaces and undertake appropriate actions

MVM143 Upgrading of Teaching Spaces 2020/21 RAG Status: GREEN

Report by Alan Gilchrist

Achievements this period

  • Camera for Vet School room G.45 has been installed and will be tested by teaching staff.
  • Discussions regarding installation dates for the Vet School 1.4x rooms have been taking place.

Issues

  • Concern raised from the Vet School over the potential noise when the 1.4x rooms in the library are to be upgraded.

Next Steps

  • Work with LST and AV installers to arrange installation dates for last year's rooms.
  • Decide on final list of rooms to upgrade this year based on limited funding.
  • Create AV designs and then tender documents for each of the new room upgrades.

MVM144 Upgrading of student computer labs, teaching and meeting room PCs 2020/21 RAG Status: GREEN

Report by Alan Gilchrist

Achievements this period

  • No progress to report due to other priorities.

Issues

  • None

Next Steps

  • Discuss replacements with local IT teams to identify suitable dates for delivery and install.
  • Peter to start to look at possible alternatives to the standard student computer lab devices.

Projects outwith the MVM Portfolio Update

Report by Alan Gilchrist and Karen Howie (LTW):

EEMeC and EEVeC

The programme has been and continues to complete projects to close down functionality on both EEMeC and EEVeC with a view to eventually decommissioning.  There is a requirement to maintain (read only) access for a period and the programme is in the process of determining those dates for its 3 year plan.

 

TEL056: Edinburgh Surgery Online Learn go-live - RAG Status: CLOSED

DTP001: Apps to User Devices - RAG Status: CLOSED

HSS022: CAHSS WAM Deployment  - RAG Status: BLUE - Closed

TEL057: Learn Foundations - RAG Status: GREEN

Achievements in the last period

  • Continued data analysis from the Summer data collection.

  • Continued Phase Three work streams.

  • Continued to look at the School migration reports (x20).

  • Scheduled in Lesson Learned sessions for each College.

  • Begun Phase Three programme of engagement

  • Begun Phase Three programme of user experience

Issues

  • None to report

Next Steps

  • Continue data analysis from the Summer data collection.

  • Continue Phase Three work streams.

  • Hold in Lesson Learned sessions for each College and prepare lessons learned reports.

  • Continue Phase Three programme of engagement

  • Continue Phase Three programme of user experience

 

Section Four: Closed or Withdrawn Projects

Only those projects closed from 28th June 2019 onwards are included in this table. A full history of completed projects is available on the programme's website.

Project Info Project Manager's Commentary
MVM126 Upgrading of student computer labs, teaching and meeting room PCs 2018/19 This project started in October 2018 and closed on 28 June 2019. The Closure report is now available.
MVM129 Support for OSCEs in Practique for MBChB This project started in June 2018 and closed on 28 June 2019. The Closure Report is now available.
MVM131: Migration of 12 applications developed in Biomedical Sciences to central support - Analysis & Strategy This project started in December 2018 and closed on 28 June 2019. The Closure Report is available to view.
MVM133: CMVM Curriculum Mapping Tool - Requirements This project started in April 2019 and closed on 9th August 2019.  The Closure Report is available to view. 
MVM130: Upgrading of teaching spaces 2018/19 This project started in October 2018 and closed on 1st November 2019. The Closure Report is available to view.
MVM134 MBChB Evaluation System This project started in September 2019 and closed on 8th April 2020. The Closure Report is available to view.
MVM137 Upgrading of Student Computer Labs , Teaching and Meeting Room PC 19/20 This project started in December 2019 and closed on 6th July 2020. The Closure report is available to view.
MVM132 MBChB ranking reports in BI Suite This project started in April 2019 and closed on 31 July 2020. The Closure report is available to view.
MVM138 Vets EMS Placement Management This project started in January 2020 and closed on 29 September 2020. The Closure Report is available to view.
MVM112 Technology to support simulation teaching This project started in September 2017 and closed on 30 September 2020. The Closure Report is available to view.
MVM135 Upgrading of Teaching Spaces 2019/20 This project started in December 2019 and closed on 30 September 2020. The Closure Report is available to view.
MVM516 BMS - Honours Project Portal Future Support  This project started in May 2019 and closed on 19 October 2020. The Closure Report is available to view.

Section Five: Programme Meeting Minutes

Minutes for all programme meetings are available on the MVMLAT website. Only the most recent five meetings' direct links are included in this table:

Date

Comments

10 November 2020 Programme Review Monthly Meeting - October 2020
13 October 2020 Programme Review Monthly Meeting - September 2020
7 September 2020  Programme Review Monthly Meeting - August 2020
10 August 2020 Programme Review Monthly Meeting - July 2020
16 July 2020 Programme Review Monthly Meeting - June 2020

Section Six: MVM Portfolio Projects Update 

The MVM Portfolio contains three programmes: CMVM Learning and Teaching - MVMLAT (this programme); CMVM Business Administration - MVMBUS and CMVM Research - MVMRES. Information on current work in MVMBUS and MVMRES are available on the following websites:

AttachmentSize
Image icon mvmlat_fl_nov_20.png95.33 KB
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Programme Info