Report for September 2016

Report Date
September 2016

Report by Muriel Mewissen on behalf of Alan Gilchrist (MVMLAT Programme Managers)

for Sheila Lodge (MVMLAT Portfolio Owner)

and Paul Clark (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)

 

Section One: Programme Commentary, RAG and Resource Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary:

The MVM Learning and Teaching Programme has 2 projects on-going and its overall status is GREEN.

  1. MVM032 Speedwell Service Implementation: his is a 15/16 project continuing in 16/17. This project is GREEN.
  2. MVM105 Strategy for the upgrade of our teaching spaces (annual): A "Transform" project with an estimate of 50 days to completeThis project is GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Resources to end September 2016

NB: The chart below only shows IS Apps resources.

 

Forward Look - September 2016

 

 

Section Two: Projects Not Started

At least another 17 projects will be started this year, and possibly more.

Project Info Programme Manager's Commentary
MVM101 Connectivity - on-campus and off-campus

To start on 17 Oct 2016

MVM102 Innovative Technology Review

To start in Nov 2016

MVM103 Mobile Device Management

To start on 10 Oct 2016

MVM104 Strategy for the upgrade of our computer labs (annual)

To start in Jan 2017
MVM106 Student Print Strategy

To start in Nov 2016

MVM107 Technology to support assessment and feedback

To start on 24 Oct 2016

MVM108 Technology to support Attendance and Monitoring

To start in Nov 2016

MVM109 Technology to support communications with potential students

To start in Nov 2016

MVM110 Technology to support Open Educational Resources (OER)

To start in Nov 2016

MVM111 Technology to support short-notice communications to students

To start on 3 Oct 2016

MVM112 Technology to support simulation teaching

To start on 24 Oct 2016

MVM113 Technology to support student portfolios

To start in Nov 2016

MVM114 Technology to timetabling and room booking

To start in Nov 2016

MVM115 Technology to support TransNational Education (TNE)

To start in Nov 2016
MVM116 Video Strategy

To start on 10 Oct 2016

MVM117 Virtual Desktop and software access

To start in Nov 2016

MVM120 Windows 10 rollout to computer labs

To start in Nov 2016

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

MVM032:

Speedwell Service Implementation

 

 

Category: Discretionary

Milestones

27-Sep-2016  Acceptance Review
05-Oct-2016  Delivery
19-Oct-2016  Deployment Review
16-Nov-2016  Closure

 

RAG Status

GREEN

Report by Tim Gray for September 2016

Achievements this period

  • Load testing delayed and in progress
  • Apply version 1.5 to all environments
  • UAT for version 1.5 completed successfully
  • Tested running exam simultaneously over two areas. Basic tes was successful but issues around delivery still under investigation 
  • Project team met with Speedwell to discuss road map and requirements
  • OLS drafted and circulated

Issues

  • Accpetance review delayed slightly due to load testing

Next Steps

  • Complete load testing
  • Deploy Vets instance to new LIVE environment
  • Agree SLA with Speedwell
  • Complete and sign off OLA

MVM105:

Strategy for the upgrade of our teaching spaces (annual)

 

 

Category: Discretionary

Milestones

30-Jun-17 Closure

 

RAG Status

GREEN

Report by Alan Gilchrist for September 2016

Achievements:

  • Gather input from staff on upgrade plan
  • Draw priority list for upgrade
  • Input into Estates committee report for RDEC funding

Issues:

  • None

Next Steps:

  • External contract to help LST team to manage the project, design the new teaching space and carry out procurement.
  • Meeting to discuss upgrades at Little France scheduled for 4 October 2016.
  • Other campus meeting to be scheduled.
  • Review priority list of upgrades after all consultations

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

MVM024 Integration and adoption of ISFM

This is a 15/16 project, potentially continuing in 16/17. This project was suspended in May 2016.  

Programme Info

Documentation