Report for November 2016
- Report Date
- November 2016
Report by Muriel Mewissen on behalf of Alan Gilchrist (MVMLAT Programme Managers)
for Sheila Lodge (MVMLAT Portfolio Owner)
and Paul Clark (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary:
Two projects have started this month:
The procurement of online examination software is the top priority for this programme and the CMVM portfolio. Improving the students experience is a priority for CMVM, and assessment and feedback have been noted as the principal area for improvement.
The overall status of the MVM Learning and Teaching programme is GREEN. Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Resources to end November 2016
Forward Look - November 2016
Section Two: Projects Not Started
Another 15 projects may start later this year, these are:
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||
Speedwell Service Implementation Category: Discretionary Milestones
RAG Status GREEN |
Report by Tim Gray for November 2016 Achievements this period
Issues
Next Steps
|
||||||
Connectivity - on-campus and off-campus
Category: Discretionary Milestones
RAG Status GREEN |
Report by Alan Gilchrist for November 2016 Achievements:
Issues:
Next Steps:
|
||||||
Strategy for upgrade of our teaching spaces (annual)
Category Discretionary Milestones
RAG Status GREEN |
Report by Alan Gilchrist for November 2016 Meetings have now taken place at the Vet School and the Central area where the following decisions have been made: Vet School:
Eddy O’Hare is currently working on the installation designs for the rooms, so that tender can go out before Christmas. Installation dates currently being looked at are during Easter and Summer 2017 Central Area:
Update on Chancellor’s Building rooms:
Meeting with Panasonic rep organised by Eddie O’Hare where discussion took place regarding projector options for Vet School rooms and Chancellor’s Building lecture theatre A. Have been advised that laser projection and 3D does not work well, so likely that 3D will not be installed in the Chancellor’s Building. Have been trying to get some additional information from Olympus regarding their installation in the RIE surgical theatre. Quote has been received for the SMOTS installation in the Western General Hospital and decision will be to install SMOTS facilities in the 5 MEC seminar rooms as well as the rack mounted SMOTS recorder (will be requesting this be installed in the MEC switch room). |
||||||
Procurement of an online application to support assessment and feedback for MBChB Category: Discretionary Milestones
RAG Status GREEN
|
Report by Paul De'Ath for November 2016 Achievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
MVM024 Integration and adoption of ISFM | This is a 15/16 project, potentially continuing in 16/17. This project was suspended in May 2016. |