Report for August 2017

Report Date
August 2017
Report by Muriel Mewissen on behalf of David Perry and Anthony Davie (MVMRes Programme Managers)                             
for Charles ffrench-Constant and Paul McGuire (MVMRes Portfolio Owners)
and Paul Clark (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Commentary:

This new session 2017/18 started with ten ongoing projects, two of them are managed by Project Services staff.

Four projects have a AMBER RAG status:

The remaining six projects have a GREEN status. The overall status of the MVMRes programme is AMBER.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

Forward Look - August 2017

 

Section Two: Projects Not Started

No additional projects are expected to start in 2017/18 at present.

Another project is being considered for prioritisation in future years, and currently listed under MVMRes Programme Session 2018/19.

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

MVM301:

College Software as a Service (SaaS) Strategy

Category: Discretionary

 

Milestones
Target Date Title
30-Sep-17 Closure

 

RAG Status

GREEN

Report by David Perry for August 2017

Achievements
  • Built a RedCap (Clinical Trial Database Toolkit) system for Reproductive Health
  • Rstudio Server Pro working well in it's clustered form
  • VoiceBank server working well
Issues
  • OMERO image management system was not developed as the pilot project (Comparative Pathology) did not receive funding.
Next Steps
  • Relicense the RStudio Server Pro environment.
  • Review configuration of VoiceBank server to potentially be more elastic and not have all aspects of the system stack 'always on'; will help reduce CPU/Hour costs.
  • Review security scanning and remedial actions for VoiceBank system hosted on Eleanor.
  • Report on progress to be completed by the end of September.

MVM302:

Compute and High Performance Compute Strategy

 

 

Category: Discretionary

Milestones

Target Date Title
31-Dec-17 Closure

 

RAG Status

AMBER

Report by Anthony Davie for August 2017

Achievements
  • PM completed revision of initial draft of project brief.
  • IT Programme Manager sent revised version of project brief to check.
Issues
  • Programme Business Owner still to score priority for MVM302 in Research business context.
  • Feedback on re-drafted request for project template outstanding from Portfolio Manager and Programme Business Owner for MVMRES
Next Steps
  • Assuming this project is approved, progress review of initial draft of project brief.
  • PM to engage with potential project stakeholders and circulate draft project brief
  • PM to arrange initial stakeholder meeting, with view to sign-off project brief and initiate project.

 

MVM304:

Electronic Lab Notebook

Category: Discretionary

 

Milestones
Target Date Title
30-Sep-17 Closure

 

RAG Status

GREEN

Report by David Perry for August 2017

Achievements
  • No progress since last month
  • Within IGMM (MVM) there is also a parallel effort to digitise paper lab notebooks and then host the .pdf version online.
Issues
  • Engagement with College research support network to promote
Next Steps
  • Continue to support the Noor Gammoh's adoption of an ELN.
  • Write up final report for the project.

MVM305

Flexible Server hosting 

Category: Discretionary

Target Date Title
31-Mar-18 Closure
 
RAG Status

GREEN

Report by Anthony Davie for August 2017

Achievements
  • PM working on first draft of project brief.
Issues
  • Some continued delays to Research Services infrastructure refreshes (Datastore refactor, expansion and backup expansion) pushing back start time for preliminary discussions.
Next Steps
  • PM to complete 1st draft of project brief.

  • PM to engage with potential project stakeholders and circulate draft project brief.

  • PM to arrange initial stakeholder meeting, with view to sign-off project brief and initiate project.

MVM306

Network IT improvements

Category: Discretionary

 

Target Date Title
31-Dec-17 Closure
 
RAG Status

GREEN

Report by Anthony Davie for August 2017

Achievements
  • Equipment (new network switches) arrived in Aug '17.
  • Held initial sponsor meeting with new PM's
    • agreed to re-focus scope and concentrate on priority deliverables:
      • formation of "virtual network team"
      • adoption of HGU network by ITI CIS
      • roll-out of new network switches
  • PM's adjusting draft project brief
  • Kick-off meeting with senior project members being arranged by Jens for Sept '17, to agree revised project brief
Issues
  • Problem with PM resourcing resolved by assigning new PM's (Sarfraz Mohammed and Jens Brincker)
Next Steps
  • PM's to engage with potential project stakeholders and circulate draft project brief.

  • PM's to arrange initial stakeholder meeting, with view to sign-off project brief and initiate project.

MVM308

Research computing induction

Category: Discretionary

 

Target Date Title
31-Jul-18 Closure
 
RAG Status

AMBER

Report by Anthony Davie for August 2017

Achievements
  • None
Issues
  • Ongoing challenges with resourcing PM for project, with primary focus from campus resource limited by holiday period and high levels of on-going business workload.
Next Steps
  • Assign project manager and move towards project briefing.

 

MVM310:

Information Governance Standards

Category: Discretionary

 

Milestones
Target Date Title
30-Sep-17 Closure

 

RAG Status

GREEN

Report by David Perry for August 2017

Achievements
  • Continue engagement with RSS016 for a real world example from the College
Issues
  • None

Next Steps
  • Write up final project report during September 2017

 

MVM312:

Walled Garden Pathfinder

Category: Discretionary

 

Milestones
Target Date Title
30-Sep-17 Closure

 

RAG Status

GREEN

Report by David Perry for August 2017

Achievements
  • Work has started on the processes to automatically ingest data generated on laboratory devices that exist outwith the Walled Garden.

  • Planning of future migration of the pilot CJD Walled Garden into the new Data Safe Haven; expected to be done March 2018.

Issues
  • None
Next Steps
  • Complete process for automated data ingest; ensure that this process will be applicable for the new Data Safe Haven too.
  • Review the secure printing processes for the Walled Garden to ensure that paper copies of restricted data are not seen by unauthorised parties.
  • Migrate more project data folders from the old CJD system in to the new Walled Garden. 
  • This project will be written up and concluded within September 2017.

MVM314:

SEBI - Data Collection and Modelling

Category: Discretionary

 

Milestones
Target Date Title
27-Oct-2017 Deliver Community of Practice Data Platform (SEBI-2)
10-Nov-2017 Livestock interventions data platform (SEBI-1)
22-Dec-2017 Data Transformation workflows
26-Jan-2018 Agree long term support arrangements
28-Feb-2018 Closure
 
RAG Status

AMBER

Report by Colin Watt for August 2017

Achievements in Last Period

  • Outcomes of the discussions on Community of Practice are leading to consensus that the partners are now looking for a platform to store metadata about the livestock data that exists, rather than the datasets themselves.
  • A separate strand of work within SEBI is working on a partnership in Ethiopia and this is likely to provide data sets on livestock and interventions.
  • There have been changes in the SEBI project team, with new team members to be confirmed.
  • A reshaping of the milestones is now in progress but due to resource conflicts / SEBI team availability this has not yet been approved; milestones currently provisional.

Issues

  • No major issues, though ongoing discussion (SEBI Programme Managers, partners and .BMGF) have resulted in delays to defining some of the technical deliverables for each of the SEBI 1 and SEBI 2 strands.
  • SEBI team are having ongoing discussion with BMGF and the other partners on overall and immediate priorities; as a result the main input from IS Apps has been PM time until SEBI are able to define the data transformation processes required; PM is working with the SEBI team to define what is required and reshape the milestones; at present it is not anticipated that the budget estimate for IS Apps days will increase significantly, but the main technical outputs will now be in 17/18.

Next Steps

  • Define and agree scope changes with project team and sponsor for delivery of metadata and livestock datasets platforms.
  • Review budget and resourcing for potential strand of work with Ethiopia datasets.

Current RAG status is AMBER due to the need to revise the overall timeline due to the technical deliverables being pushed back.

MVM315

REACH

Category: Discretionary (Sponsor Funded - Usher Institute)

 

Milestones

Target Date Title
25-Aug 2017 Proof-of-concept available for demo to funder
6-Oct 2017 Go-Live , allowing public users to register for the REACH service
 
RAG Status

AMBER

Report by Jamie Thin for August 2017

 

Achievements in Last Period
  • Front-end Drupal 8 website changes delivered in TEST
  • Drupal 8 Web form created in TEST
  • Custom Drupal module delivered to integrate the Drupal web form to back-end MySQL database, and implemented in TEST
  • Web form handed over to Abby King for user testing in TEST
  • Dialogue started with Information Security team to seek advice for configuration of back-end database in LIVE
Issues
  • Need to agree if 'Encryption at rest' on MySQL database is a mandatory requirement
  • Need to agree minimum back-end database security requirements to get the new service LIVE by Mon 2-Oct 2017. Subject to ongoing funding being secured by the REACH project team , the backend database is expected to move to the new 'UoE data safe haven' in the future - so the current infrastructure will be an interim holding solution
Next Steps
  • Complete technical design for back-end database infrastructure
  • Build new MySQL process (instance) for LIVE
  • WGI to create new 'TEST' web front-end with snaphot copy from Live - for testing their Drupal 8 migration to new 'TEST' [Existing TEST will become new 'DEV' env]
  • WGI team to deploy their Drupal 8 changes to new 'TEST'
  • Deploy changes to LIVE infrastructure w/c 25/09/17 before Go-Live date for Registration form on Mon 2nd Oct 2017
  • Work on Data exports and workflows can follow the 2nd Oct go-live date - as that is work required to support the sharing of the data , and data needs to be collected first during Oct

Current RAG status is AMBER due to delay in planning.

 

Section Four: Closed or Withdrawn Projects

 

None yet this session