Report for June 2019

Report Date
June 2019

 

Report by Muriel Mewissen on behalf of David Perry and Anthony Davie (MVMRes Programme Managers), for Charles ffrench-Constant and Paul McGuire (MVMRes Programme Owners), Sheila Fraser (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)

 
Distribution:
  • Institute IT meetings / Service Review meetings.
  • College Research Support Network (RSN) meeting.
  • College Research Committee
  • Excerpts taken into CSG report

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During June, conversations have re-started on MVM314: SEBI - Data Collection and Modelling. A way forward has been identified to move to a hosted service for the Tableau application. The project will be unsuspended and work resuming next month.

Other projects are continuing to suffer from delays with input from stakeholders and lack of availability. It is now expected that MVM302: Compute and High Performance Compute Strategy and MVM308: Research computing induction will continue into next session. These projects are reporting an AMBER RAG status

The overall status of the MVMRes programme is AMBER.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Forward Look - June 2019

 

Section Two: Projects Not Started

No additional project will be started this session.

 

Section Three: Projects in Progress

 MVM302: Compute and High Performance Compute Strategy - RAG Status: AMBER

Report by Barry Horne

Achievements this period

  • None

Issues

  • Moved to work for ITI, spend 1 day per month working with CMVM.
  • Awaiting feedback from Portfolio owner to determine next steps.

Next Steps

  • Close project

MVM305: Flexible Server hosting  - RAG Status: SUSPENDED

Report by Muriel Mewissen

Achievements this period

  • None, project is currently suspended

Issues

  • New PM to be recruited into Easter Bush MVM team

Next Steps

  • Status to be reviewed once new PM is in place.

MVM308: Research computing induction - RAG Status: AMBER

Report by Paul De'Ath

Achievements this period

  • Project brief presented to majority of stakeholders - all approved

Issues

  • N/A no new risks or issues

Next steps

  • Distribute project brief wider
  • Obtain all content associated with inductions - consider utilising a new tab on intranet (mvm522) for holding
  • Create recommendations and confirm estimate for budget (TBC 10 days)

MVM311: CMVM Data Storage Strategy - RAG Status: GREEN

Report by Geoff Cropley

Achievements this period

  • P​​​​​roject closure has been delayed due to emerging strategic changes
  • Closure milestone to be moved to 12 July 2019

Issues

  • None

Next Steps

  • Close Project

MVM314: SEBI - Data Collection and Modelling - RAG Status: SUSPENDED

Report by Colin Watt

Achievements this period

  • The project is scheduled to be unsuspended next month. Agreement to moved Tableau to a hosted setup.

 

Section Four: Closed or Withdrawn Projects

Project Info

Project Manager's Commentary
MVM309 Scientific administration process enhancements Decision to withdrawn the project has been agreed at the  Programme Review Monthly Meeting - March 2019. The business is not yet ready for this and a lot of background is needed in several areas before this work could start.
MVM315: REACH

This project was started in July 2017 nd was closed on the 21 December 2018.  The Completion Report is available to view.

MVM306: Network IT improvements

This project was started in April 2017 and was closed on the 28 September 2018. The Completion Report is available to view.

 

Section Five: Programme Meeting Minutes

Date Comments
24 June 2019 Programme Review Monthly Meeting - June 2019
23 May 2019 Programme Review Monthly Meeting - May 2019
1 May 2019 Programme Review Monthly Meeting - April 2019
27 March 2019 Programme Review Monthly Meeting - March 2019
28 February 2019 Programme Review Monthly Meeting - February 2019
29 January 2019 Programme Review Monthly Meeting - January 2019
21 November 2018 Programme Review Monthly Meeting - November 2018
30 October 2018 Programme Review Monthly Meeting - September 2018
27 September 2018 Programme Review Monthly Meeting - August 2018
24 July 2018 Programme Review Monthly Meeting - July 2018