Report for September 2019
- Report Date
- September 2019
Report by Muriel Mewissen on behalf of David Perry and Anthony Davie (MVMRes Programme Managers), for Charles ffrench-Constant and Paul McGuire (MVMRes Programme Owners), Sheila Fraser (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)
Distribution:
-
Institute IT meetings / Service Review meetings.
-
College Research Support Network (RSN) meeting.
-
College Research Committee
-
Excerpts taken into CSG report
Section One: Programme Commentary, RAG and Resources Update
Commentary
During September, agile developments are progressing well in MVM316: Fragile X Registry website. However, some amount of scope creep and low of availability of sponsor means that the velocity of the sprint will be reviewed and user stories re-prioritised to align with a minimum viable product. An option for the developments to be less intense but over longer period of time is currently under review. The project is AMBER because of this re-planning.
Another two projects are AMBER due to ongoing delay over closure:
MVM308 Research computing induction is reporting a RED status following an agreement to extend the project to July 2020 milestones with the effort still to be estimated and budget confirmed.
The overall status of the MVMRes programme is AMBER.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Forward Look - September 2019
Section Two: Projects Not Started
No additional project has been identified to start this session.
Section Three: Projects in Progress
MVM302: Compute and High Performance Compute Strategy - RAG Status: AMBER Report by Anthony Davie for August 2019 - No update provided in SeptemberAchievements this period
Issues
Next Steps
|
MVM305: Flexible Server hosting - RAG Status: SUSPENDED Report by Muriel MewissenAchievements this period
Issues
Next Steps
|
MVM308: Research computing induction - RAG Status: RED Report by Susan Ridder-PatrickAchievements this period
Issues
Next Steps
|
MVM311: CMVM Data Storage Strategy - RAG Status: GREEN Report by Muriel MewissenAchievements this period
Issues
Next Steps
|
MVM314: SEBI - Data Collection and Modelling - RAG Status: AMBER Report by Colin WattAchievements this period
Issues
Next Steps
|
MVM316: Fragile X Registry website - RAG Status: AMBER Report by Kevin HoneAchievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
No project has been completed this session yet.
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
20 September 2019 | Programme Review Monthly Meeting - September 2019 |
24 August 2019 | Programme Review Monthly Meeting - July & August 2019 |
24 June 2019 | Programme Review Monthly Meeting - June 2019 |
23 May 2019 | Programme Review Monthly Meeting - May 2019 |
1 May 2019 | Programme Review Monthly Meeting - April 2019 |
27 March 2019 | Programme Review Monthly Meeting - March 2019 |
28 February 2019 | Programme Review Monthly Meeting - February 2019 |
29 January 2019 | Programme Review Monthly Meeting - January 2019 |
21 November 2018 | Programme Review Monthly Meeting - November 2018 |
30 October 2018 | Programme Review Monthly Meeting - October 2018 |