Report for September 2022

Report Date
September 2022

 

Report by Muriel Mewissen on behalf of Anthony Davie (MVMRes Programme Manager), for Jennifer Cusiter (MVMRes Programme Owner) and Sheila Fraser (MVM Portfolio Manager)

 
Distribution:
  • Institute IT meetings / Service Review meetings.
  • College Research Support Network (RSN) meeting.
  • College Research Committee
  • Excerpts taken into CSG report

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During September, the only project in the programme is progressing as planned.

The overall status of the MVMRes programme is GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Forward Look - September 2022

 

Section Two: Projects Not Started

Project Info Notes
No new project to be started this session

CMVM has a budget of 150 ring fenced days for 22/23. The start of year allocations are set in the Portfolio record 67 and include an allocation of

 

Section Three: Projects in Progress

MVM305: Flexible Server hosting  - RAG Status: SUSPENDED

Report by Muriel Mewissen

Achievements this period

  • None, project is currently suspended.

Next Steps

  • Status to be reviewed at the next Programme meeting

MVM317 Lothian Health Board Framework Agreement Implementation - RAG Status: GREEN

Report by Sue Woodger

Achievements in last period

  • Sponsor started a mindmap of what will be required to take project forward
  • Initial orientation on 4/10/22 for new business analyst taking over from current PM/BA

Issues

  • None this month

Next Steps

  • PM to progress mindmap to support presentation paper to College
  • PM to update raci matrix
  • PM to hand over business analysis to new BA
  • PM to hand over project management to new PM stating on 17 Oct
  • Replanning of project will be required and a chaneg record to be added to update the delivery date

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's commentary
N/A No project has been completed in this session.

 

Section Five: Programme Meeting Minutes

Date Comments
15 Septembre 2022 Programme Review Monthly Meeting - September 2022
15 August 2022 Programme Review Monthly Meeting - July & August 2022
15 June 2022 Programme Review Monthly Meeting - June 2022
10 May 2022 Programme Review Monthly Meeting - April & May 2022
14 March 2022 Programme Review Monthly Meeting - February & March 2022
17 January 2022 Programme Review Monthly Meeting - January 2022 
14 December 2021 Programme Review Monthly Meeting - December 2021
17 November 2021 Programme Review Monthly Meeting - November 2021
13 October 2021 Programme Review Monthly Meeting - October 2021
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.