Report for November 2016
- Report Date
- November 2016
Report by Muriel Mewissen on behalf of David Perry and Anthony Davie (MVMRes Programme Managers)
for Brian Walker and Paul McGuire (MVMRes Portfolio Owner)
and Paul Clark (MVM Portfolio Manager) and Catherine Elliot (MVM Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary:
Five on-going projects in MVM Research Programme are in progress. However the sheer volume of work combined with higher priority and urgent work in this programme has meant that work on the MVM304 Electronic Lab Notebooks has stalled. The decision has been taken to suspend the project until stakeholders are able to fully engaged, later next year. The start of any additional project has also been delayed until March 2017.
Four of these projects are GREEN and progressing well. These are:
- MVM301 College Software as a Service (SaaS) Strategy
- MVM310 Information Governance Standards
- MVM312 Walled Garden Pathfinder
- MVM314 SEBI - Data Collection and Modelling
One project, MVM302 Compute and High Performance Compute Strategy, is experiencing issues due to underlying Eddie service stability problems within CMVM. As a consequence, this project is effectively on hold until such times as Eddie service stability resumes (projected February 2017).
The overhaul status is RED.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Resources to end November 2016
Forward Look - November 2016
NB: The chart below only shows IS Apps resources.
Section Two: Projects Not Started
The start of any new project has been delayed until March 2017 because current, higher priority projects have taken over existing resources and stakeholder engagement.
Project Info | Programme Manager's Commentary |
To start in Mar 2017 |
|
To start in Mar 2017 | |
MVM306 Network Infrastructure Strategy |
To start in Mar 2017 |
MVM307 REF readiness |
To start in Mar 2017 |
MVM308 Research Computing Induction |
To start in Mar 2017 |
MVM309 Scientific Administration Process Enhancements |
To start in Mar 2017 |
MVM311 Storage Strategy |
To start in Mar 2017 |
MVM313 Research Teaching Strategy |
To start in Mar 2017 |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||
College Software as a Service (SaaS) Strategy
Category: Discretionary Milestones
RAG Status GREEN |
Report by David Perry for November 2016 |
||
Compute and High Performance Compute Strategy
Category: Discretionary Milestones
RAG Status RED |
Report by Anthony Davie for November 2016 Achievements
Issues
Next steps
|
||
Category: Discretionary Milestones
RAG Status GREEN |
Report by David Perry for November 2016 |
||
Information Governance Standards
Category: Discretionary Milestones
RAG Status GREEN |
Report by David Perry for November 2016 |
||
Category: Discretionary Milestones
RAG Status GREEN |
Report by David Perry for November 2016 |
||
SEBI - Data Collection and Modelling
Category: Discretionary Milestones (NB to be confirmed during planning)
RAG Status GREEN |
Report by Colin Watt for November 2016
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary | |
N/A |
Projects in the MVM Research programme for 16/17 are currently in progress or are yet to start. |