Report for September 2022
- Report Date
- September 2022
During September
Section One: Programme Commentary, RAG and Resources Update
Arrangements have been made for a project manager to be assigned to the Projects Website project
Forward Look
Resource Summary
Section Two: Projects Not Started
Project Information | Programme Manager's Commentary |
No projects |
Section Three: Projects in Progress
Project Information | Project Manager's Commentary |
Updating the Projects Website Category: Compliance Core Funded Milestones
|
Report by Ailsa Glass for September 2022 Achievements this period
Issues
Next steps
MilestonesTBC |
Section Four: Closed or Withdrawn Projects
Project Information | Project Manager's Commentary |
Section Five: Programme Risk Log
Risk Reference | Description | Risk Owner | Risk Status | Last Review Date |