Report for January 2013
- Report Date
- January 2013
Report compiled by Susan McKeown (IS Apps Programme Manager) for Charles Hill (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Information Management for Health and Safety project started this month and has already seen the High Level Project Brief approved and Resources secured to deliver this project using agile methods.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
Project Code (AP Number) Project Title Category: Discretionary/Compliance/Funded Planning Month Year Delivery Month Year RAG Status GREEN / AMBER / RED
| Plan
Dependencies |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
Project Code: CSG001 (AP number: AP23-011) Project Title: Information Management for Health and Safety Category: Compliance Milestones
RAG Status: GREEN | Report by Dawn Nicholls for January 2013 Achievements last period
Issues
Next steps
Full details can be seen in the Project Journal |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code (AP Number) Project Title
Discretionary/Compliance/Funded | Report by [PM] This project was closed/withdrawn on dd-mmm-yy [for closures] Please see the Completion Report / Closure Review for further information [include link]. [for withdrawn] Please see the PRICCL log for further details [include link].
|