Report for April 2023

Report Date
April 2023

Forward Look

Resource Position

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

N/A

N/A

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

CSG021

Risk Management System Upgrade

Sponsor Funded

Milestones : TBC

 

RAG Status : GREEN

 

 

 

Report by Sarah Kennington for April 2023

Achievements this period

  • Project initiation approved at Apps review
  • Project kickoff with business user and supplier to agree project delivery roles and responsibilities, time frames and outcomes
  • Resource reviews have been initiated with production and Dev tech

Issues

  • none noted

Next Steps

  • Produce planning documentation and submit for apps review next week.
  • Agree with supplier if a SSO is required or whether the new version can be housed in a hybrid solution, thereby eliminating the need for an SSO implementation.
AttachmentSize
Image icon 202304a_rag.png73.67 KB
Image icon 202304a_resources.png46.86 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No