Report for July 2023 - Draft

Report Date
July 2023

Section 1

Forward Look

 

Resource Position

 

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

N/A

N/A

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

CSG021

Risk Management System Upgrade

Sponsor Funded

Milestones :

 
Delivery Date: TBC
Close Date: TBC

RAG Status : AMBER

 

 

 

Report by Ben Armstrong for July 2023

Achievements this period

  • Continued User Acceptance Testing

Issues

  • Estates data was not transferred into the test system so that testing has not been completed; the sponsor/business lead has requested the supplier migrate Estates data for testing
  • The project delivery and closure dates have been missed but a new set of milestones (and budget for 23/24) was agreed by the sponsor on 7th July; as a result I have marked the Time and Cost RAGs as AMBER this month until the formal confirmation by Apps Review

Next Steps

  • Complete User Acceptance Testing
  • Prepare training materials

 

Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No