Report for February 2013

Report Date
February 2013

Report compiled by Susan McKeown (IS Apps Programme Manager) for Charles Hill (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

The Information Management for Health and Safety project progressed well in February and will now take a short break to accommodate leave in the team. Project reconvenes April 1.

 

 

 

 

 

 Section Two: Projects Not Started

  

 

Project InfoProgramme Manager's Commentary

Project Code (AP Number)

Project Title

Category: Discretionary/Compliance/Funded 

Planning Month Year

Delivery Month Year

RAG Status

GREEN  / AMBER / RED

 

Plan

 

 

Dependencies

 

Section Three: Projects in Progress

  

 

Project InfoProject Managers Commentary

  

Project Code: CSG001 (AP number: AP23-011)

Project Title: Information Management for Health and Safety

Category: Compliance

Milestones

 

Target dateTitle
07-Jun-2013End of development iterations
21-Jun-2013End of maintenance iteration
05-Jul-2013Closure

RAG Status: GREEN  

Report by Dawn Nicholls for February 2013 

Achievements this period

  • Two User Groups held to gather requirements in the form of User Stories.
  • Visits made to Chemistry and Biological Sciences to look at their existing systems
  • User Stories consolidated ready for prioritisation
  • Development environments set-up (Dev/Beta/Test/Live)

Issues

  • Large number of User Stories - these will need to be consolidated in line with the project objectives. H&S are considering follow-up projects to address the wider functionality highlighted.
  • Overlap with ERM functionality which may bring pressure to use ERM for haz/bio reporting - though ERM has some significant functionality missing (e.g. radioactive half-life and certificated level management)

Next steps

  • The project will now take a short break due to annual leave, reconvening on Monday 1st April
  • Prioritisation Group meeting to select User Stories for first development iterations

 

Full details can be seen in the Project Journal

 

Section Four: Closed or Withdrawn Projects

  

 

Project InfoProject Managers Commentary

  

Project Code (AP Number)

Project Title

 

Discretionary/Compliance/Funded 

Report by [PM] 

This project was closed/withdrawn on dd-mmm-yy

[for closures] Please see the Completion Report / Closure Review for further information [include link]. 