Report for October 2014
- Report Date
- October 2014
Report compiled by Dawn Nicholls on behalf of Rhian Davies (IS Apps Programme Manager) for Charles Hill (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP45-009 Essential enhancements for RETAIN Compliance Planning - January 2015 Delivery - July 2015 RAG Status : GREEN |
|
AP45-011 KX-related Technical Assistance Discretionary Planning - October 2014 Delivery - July 2015 RAG Status : GREEN |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||||
ACS033 - AP34-068 Student Application System - Enhanced Student Data Feed to Accommodation Services Funded Milestones
| Report by Colin Forrest for October 2014 Achievements in the last period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||||
CSG003 (AP45-010) Enhancements for AIR Discretionary Milestones
RAG Status : GREEN | Report by Karen Stirling for October 2014
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|
|