Report for October 2015

Report Date
October 2015

Report compiled by Dawn Nicholls on behalf of Rhian Davies (IS Apps Programme Manager) for Charles Hill (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

CSG006 OPAS Migration is still encountering issues with system outages.  Also H&S are keen to modify the firewall settings for increased security, although technical advice suggest this is not required. Options are being estimated & evaluated.

CSG009 RIR Systems Review - new in-year funded project

The overall health of the programme budget approaching the mid-year review is good, although the ongoing OPAS Migration issues may require additional funding which is yet to be agreed

 

 

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary
  

 

 Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

CSG006 (In-year)

OPAS Migration

Category: Compliance

 Milestones

25-Nov-2015Deployment sign off review
27-Nov-2015Project closure

RAG Status : AMBER

Report by Chris Konczak for October 2015

Achievements in Last Period

  • Possible solution found to the IP / Firewall issue identified. This is to create a seperate instance of SQL Server on the shared SQL server. Estimation has been put together and been circulated.

Issues

  • The old SQL server had restrictions on IP address with the firewall. The new SQL Server does not allow this as the database is now on a shared instance instead of on its own instance. We are meeting with section heads to discuss whether wheather the security we now have in place is sufficient.
  • Need to secure extra funding to persu this solution

 

Next Steps

  • Meet wtih business and sponsor to discuss this change in scope and budgets
  • If agreed by business and sponsor, implement this solution
  • Deployment Sign off Review
  • Closure

CSG007 (In-year)

Learning and Development Requirements for CSG

Category: Discretionary

 Milestones

Target dateTitle
09-Oct-2015Business Analysis
27-Nov-2015Closure

RAG Status : GREEN

Report by Ben Armstrong for October 2015

Achievements in Last Period
  • Presented recommendations to Project Sponsor and Director of CSG

Issues

  • Due to recent annual leave, the Project Manager has not yet requested a sign-off for the Business Analysis milestone.  This request will be made to the project sponsor this week but should not prevent further progress in the meantime

Next Steps

  • Organise demo of EQMS product for those managing staff learning and development
  • Arrange for those involved in delivering training to review Events Booking Admin

CSG008 (AP56-045)

RETAIN Enhancements for mass-based substances

Category : Compliance

Milestones

 

Target dateTitle
04-Nov-2015Final go-live
13-Nov-2015End of maintenance
27-Nov-2015Closure
 

RAG Status : GREEN

Report by Dawn Nicholls for October 2015

Achievements this period

  • Development iteration 2 completed 16th October, delivering functionality for adding, editing & searching for nuclear batches.  Completed User Stories can be seen on the Iteration 2 summary page
  • Development iteration 3 completed 3rd November, delivering functionality for disposing, splitting & consolidating nuclear batches.  Completed User Stories can be seen on the Iteration 3 summary page
  • Development work is now complete and go-live planned for 4th November.

Issues

  • The project has experienced a number of issues with the technical enviroment which delayed the release of completed work to UAT.  Approximately 2 days effort was spent is tracing & resolving these issues which were caused by errors in the configuration of the pre-existing instrstructure (i.e. created prior to this project).  These issues are now resolved & so the project is being reported as GREEN.

Next steps

  • Go-live of new nuclear functionality
  • Maintenance iteration for addressing any post-go-live issues
  • BI enhancements to include new data fields
  • Agree additional funding for further BI work
  • Closure

CSG009 (In-year)

RIR Systems Review

Category: Sponsor Funded

Milestones

Target dateTitle
06-Nov-2015End of planning
27-Nov-2015End of analysis
04-Dec-2015Final paper delivered
11-Dec-2015Project closure

RAG Status: GREEN

Report by Dawn Nicholls for October 2015

Achievements this period

  • Approval received to start project
  • Kick-off meeting held with Project Sponsor and Business Lead
  • Draft Project Brief produced and curculated for review
  • Resources secured

Issues

  • None this period.  Project is reported as GREEN

Next steps

  • Interviews with key stakeholders

 

 Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

AP number / project code

Project name

PM name

Category: Discretionary/Compliance/Funded

 

 

 

 

 

 

 

 

 

Documentation

Not available.