Report for June 2016
- Report Date
- June 2016
Report compiled by Dawn Holmes for Charles Hill (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
None |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||
CSG007 (In-year) Learning and Development Requirements for CSG Category: Discretionary (Sponsor funded) Milestones
RAG Status : RED | Report by Ben Armstrong for June 2016
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
CSG008 (AP56-045) RETAIN Enhancements for mass-based substances Category : Compliance | Project Manager - Dawn Holmes Closure Date - 11/12/2015 |
CSG006 OPAS Migration Category: Compliance | Project Manager - Chris Konczak Closure Date - 29/01/2016 |
CSG009 RIR Systems Review Category: DIscretionary (Sponsor funded) | Project Manager - Dawn Holmes Closure Date - 18/03/2016 |