Report for August 2016

Report Date
August 2016

Report compiled by Dawn Holmes for Charles Hill (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Forward Look to end August 2016

 

Resources Position to end August 2016

 

 

Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary
None 

 

 Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

CSG007 (In-year)

Learning and Development Requirements for CSG

Category: Discretionary (Sponsor funded)

 Milestones

Target dateTitle
16-Sep-2016Delivery
30-Sep-2016Closure

RAG Status : GREEN

Report by Ben Armstrong for August 2016

Achievements in Last Period

  • Made arrangements for further demo for CSG Directors

Issues

  • None noted

Next Steps

  • Demo to CSG Directors 6th September
  • Go/no go decision by CSG - if proceed, finalise contract which completes Delivery milestone
  • Close project

 Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary