Report for December 2016

Report Date
December 2016

 

Section One: Programme Commentary, RAG and Resources Update

 

Forward Look

 

 

Resources Position

 

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary
None  

 

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

CSG007 (In-year)

Learning and Development Requirements for CSG

Category:Discretionary (Sponsor funded)

 Milestones

closed

RAG Status : Closed

Report by Ben Armstrong for December 2016

Achievements in Last Period

  • Complete and sign contract
  • Complete EqIA
  • Arrange kick-off meetings with Business Leads
  • Close project in advance of new project request for implementation project

Issues

  • None noted

Next Steps

 none

 

CSG0010 (In Year)

CSE Replacement Servers

Category:Discretionary (Sponsor funded)

 Milestones

02-Feb-2017 Acceptance sign-off
22-Feb-2017 Deployment sign-off
17-Mar-2017 Project closure

 

RAG Status : GREEN

 

Report by David Watters for December 2016

Achievements in Last Period

  • Replacement servers built and delivered by ITI Enterprise
  • New servers configured by Dev Tech according to business requirements
  • Build stage signed off

Issues and Risks

  • None reported

Next Steps

  • Vendors on site to install software upgrades and test these
  • Business partners to undertake user testing of upgrades on new servers
  • Discussions with business partners  and Production Management about deployment

 

 

 

 

  Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary