Report for April 2017

Report Date
April 2017

 

Section One: Programme Commentary, RAG and Resources Update

 

 

Forward Look

 

Resources Position

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary
None  

 

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

CSG010 (In Year)

Sport & Exercise Replacement Servers

Category:Discretionary (Sponsor funded)

 Milestones

28-Apr-2017 Deployment sign-off Deliver
12-May-2017 Project closure Close

RAG Status : Project status is GREEN

 

Report by David Watters for April 2017

 

Achievements in Last Period

  • New infrastructure deployed into LIVE on 19/04

Issues and Risks

  • Some tweaks required to configuration of new servers

Next Steps

  • Sign off deployment
  • Prepare project completion and close project
  • Finalise answer on FASIC server

 

 

 

 

CSG011

Totara Pilot

Category: Discretionary (Sponsor funded)

 Milestones

Target date

Title

Complete

28/02/17

Planning 

YES

30/09/17

Phase 1 Delivery

NO

31/10/17 Phase 2 Delivery NO

28/11/17

Closure

NO

 

RAG Status : GREEN

Report by Ben Armstrong for April 2017

Achievements this period

  • Revised and signed off project brief
  • Gathered consistent course catalogue data from the pilot business units
  • Initial user data uploaded to Totara LMS

Issues

  • The system's requested domain name mytraining.ed.ac.uk was rejected by the naming committee; a revised request for mytraining.csg.ed.ac.uk has been submitted for approval, on the basis that a CSG sub-domain is more appropriate at this stage.  This is delaying the work to implement single sign-on which has a dependency on the domain name being in place.
  • The project had spent most of the proposal budget; however a detailed estimate was produced and approved by the project sponsor and will be submitted as a revised estimate with the planning submission.  On this basis, the cost RAG has reverted to GREEN this month.
  • An estimate for the feasibility of integrating with Event Booking is required but may not be immediately available due to resource constraints in the software development team.  A request will be submitted.

Next Steps

  • Upload of course catalogue data
  • Request software development resources for IDM feed and Event Booking integration costing/specification
  • Secure domain name and progress the single sign-on integration
  • Theming and branding of site, working with IS Graphics and Design team

 

  Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

CSG007 (In-year)

Learning and Development Requirements for CSG

Category:Discretionary (Sponsor funded)

Project closure agreed December 2016
AttachmentSize
Image icon othcsg_resourcesmar17.jpg62.28 KB
Image icon othcsg_ragmar17.jpg76.3 KB