Report for September 2019

Report Date
September 2019

Report compiled by Emma McNab

 

Section One: Programme Commentary, RAG and Resources Update

 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

 

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

CSG015

Risk Management System Procurement

Milestones - TBC

   
   
   
   
   

RAG Status

GREEN

Report for September 2019, prepared by Andy Stewart 

Achievements in Last Period:

  • Andy Stewart has been assigned as the new project manager 
  • Procurement Strategy revised 
    • Having reviewed the options going forward with Procurement, it has been agreed to 
      • pursue a solution through the G-Cloud framework as this appears to be the quickest way to market 
      • If G-Cloud proves to be unsuccessful, then there will be the requirement to issue a local ITT 

Issues:

  • None 

Next Steps:.

  • Roles and Responsibilities
    • From a G-Cloud perspective, requirement to understand how potential solutions can be evaluated with regards to both technical and accessibility requirements 
  • Determine list of potential suppliers from the G-Cloud framework 
  • Re-plan and re-estimate the project budget with regards to remaining activity  
  • Commence review of potential solutions 

 

CSG016

Industry Relationship Management (IRM) Service

Milestones

Agreed / approved at WIS after Planning (27-Sep-2019):

Milestone Due Date
End of Planning 12-Jul-2019
Map existing EI Business, Support and Training processes 04-Oct-2019
Determine support & reporting requirements / produce a Service Design Package 18-Oct-2019
Produce an Options Appraisal document 01-Nov-2019
Complete DPIA and Accessibility Review 01-Nov-2019
Delivery 08-Nov-2019
Produce a paper on CRM's technology utilised, what is to / not be consolidated and associated questions / decisions required    08-Nov-2019
Closure 15-Nov-2019

 

RAG Status:  GREEN

 

Report for September 2019, prepared by Kevin Hone

Achievements this Period

  • The Project has undergone a restructure with both a new BA (Elaine Wighton) and PM (Kevin Hone) appointed and in place
  • Further workshops were undertaken in order to fully understand the EI existing processes for Business, Support and Training
  • The Project has been re-planned, with milestones and budget agreed and submitted to WIS for approval 27-Sep-2019  

 

Issues

  • Risk #5:  Availability of Key Resource  (AMBER)  -  The Project has experienced further issues obtaining availability from various key resource, again due to annual leave commitments and illness, as well as leavers.  This has impacted the timeline and will need careful review
  • Risk #10:  Agreement of a Standard Service Definition Across all Customers of IRM Might not be Reached  (AMBER)  -  During initial analysis and in light of the fact that the existing support for the IRM service is not fully defined / documented it would appear that there is a risk that existing Customers of IRM are utilising CRM in different methods, if a common / standard approach cannot be adopted this could have consequences to providing Support

 

Next Steps

  • Continue to work through / look to complete the Project deliverables:
    • Begin requirements workshops with Service Management and EI to produce the Service Design Package
    • Begin works on the Options Appraisal document / engage with Procurement
    • Undertake a DPIA workshop
    • Engage with the Accessibility Officer and conduct an Accessibility Review

 

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

 