- Report Date
- September 2019
Report compiled by Emma McNab
Section One: Programme Commentary, RAG and Resources Update


Section Two: Projects Not Started
Project Info |
Programme Manager's Commentary |
|
|
Section Three: Projects in Progress
Project Info |
Project Managers Commentary |
CSG015
Risk Management System Procurement
Milestones - TBC
RAG Status
GREEN
|
- Report for September 2019, prepared by Andy Stewart
Achievements in Last Period:
- Andy Stewart has been assigned as the new project manager
- Procurement Strategy revised
- Having reviewed the options going forward with Procurement, it has been agreed to
- pursue a solution through the G-Cloud framework as this appears to be the quickest way to market
- If G-Cloud proves to be unsuccessful, then there will be the requirement to issue a local ITT
Issues:
Next Steps:.
- Roles and Responsibilities
- From a G-Cloud perspective, requirement to understand how potential solutions can be evaluated with regards to both technical and accessibility requirements
- Determine list of potential suppliers from the G-Cloud framework
- Re-plan and re-estimate the project budget with regards to remaining activity
- Commence review of potential solutions
|
CSG016
Industry Relationship Management (IRM) Service
Milestones
Agreed / approved at WIS after Planning (27-Sep-2019):
RAG Status: GREEN
|
- Report for September 2019, prepared by Kevin Hone
Achievements this Period
- The Project has undergone a restructure with both a new BA (Elaine Wighton) and PM (Kevin Hone) appointed and in place
- Further workshops were undertaken in order to fully understand the EI existing processes for Business, Support and Training
- The Project has been re-planned, with milestones and budget agreed and submitted to WIS for approval 27-Sep-2019
Issues
- Risk #5: Availability of Key Resource (AMBER) - The Project has experienced further issues obtaining availability from various key resource, again due to annual leave commitments and illness, as well as leavers. This has impacted the timeline and will need careful review
- Risk #10: Agreement of a Standard Service Definition Across all Customers of IRM Might not be Reached (AMBER) - During initial analysis and in light of the fact that the existing support for the IRM service is not fully defined / documented it would appear that there is a risk that existing Customers of IRM are utilising CRM in different methods, if a common / standard approach cannot be adopted this could have consequences to providing Support
Next Steps
- Continue to work through / look to complete the Project deliverables:
- Begin requirements workshops with Service Management and EI to produce the Service Design Package
- Begin works on the Options Appraisal document / engage with Procurement
- Undertake a DPIA workshop
- Engage with the Accessibility Officer and conduct an Accessibility Review
|