Report for April 2020

Report Date
April 2020

Report compiled by Emma McNab

Section One: Programme Commentary, RAG and Resources Update

 

Forward Look

 

The Programme is continuing through the challenges presented by the current Covid-19 situation.  There are 2 projects in progress and 1 yet to be started this year.

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

CSG018: IRM Business School

 

This project will be progressed and is due to be initiated within May 2020. 

 

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

CSG015

Risk Management System Procurement

Milestones 

The following milestones have been agreed with the project sponsor, but may require to be adjusted after the completion of the initial user training and familiarisation scheduled for Thursday 14th May 

Milestone Due Date
System Implementation t05-Jun-2020
System acceptance  19-Jun-2020
System Roll Out 17-Jul-2020
Project Closure 14-Aug-2020

RAG Status

GREEN

Report for April 2020 , prepared by Andy Stewart 

Achievements in Last Period:

  • Completed project implementation plan 
  • Supplier led user training and familiarisation scheduled for Thursday 14th May 
  • Contact established with supplier helpdesk regarding Single Sign On configuration 

Issues:

  • Due to the lack of Development Technology resource availability, it has not been possible to progress the Single Sign On configuration

Next Steps:.

  • Formally extend project to incorporate system implementation 
  • Commence technical configuration regarding Single Sign On
  • Initial user training to be completed 
  • Commence system configuration 
  • Establish communication strategy for system users 

 

 

CSG017

IRM Intellectual Property (IP) Team Onboarding

Milestones

Milestone Due Date
IRM Migration Preparation - Test 15-May-2020
IRM Migration Completed - Test 22-May-2020
IRM Migration Review - Test 12-Jun-2020
IRM Migration User Training 19-Jun-2020
IRM Migration Sign Off - Test 19-Jun-2020
IRM Migration Go-Live 26-Jun-2020
IRM Migration DSOR 10-Jul-2020
Closure 17-Jul-2020

 

RAG Status:  GREEN

 

Report for April 2020, prepared by Andrew Stewart

Achievements this Period

  • Project Planning phase completed 
  • Business requirements defined and signed-off the Tech Transfer team
  • Definition of required reports commenced 
  • IRM sandbox development commenced 
  • Digital Training 
    • Demonstration of Collaborate scheduled for the project team on Monday 11th May 
    • User training schedules issued 

Issues

  • Requirement to clarify on-going strategy regarding the creation of reports 

Next Steps

  • Finalise reporting requirements 
  • Continue IRM Sandbox build 
  • Digital Training 
    • Define on-line training mechanism 
    • Commence user training material 
  •  
   

Section Four: Closed or Withdrawn Projects

CSG016: Industry Relationship Management (IRM) Service - Closed 

Project Info Project Managers Commentary

 

AttachmentSize
Image icon csgapril2.png42.36 KB
Image icon csgapril.png77.43 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No
Escalated to
Deputy CIO