Report for July - Draft

Report Date
July 2013

Report compiled by Susan McKeown (IS Apps Programme Manager) for Charles Hill (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section Five: New Approved Projects from 13/14 Annual Plan

Section One: Programme Commentary, RAG and Resources Update

The Information Management for Health and Safety project has noted 9 days of carryover into 13/14 which had already been provisionally allocated days in next year's Programme budget. Please note that the first release of the software took place in July as planned. 

 

 

 

 

Section Two: Projects Not Started

  

Project InfoProgramme Manager's Commentary

Project Code (AP Number)

Project Title

Category: Discretionary/Compliance/Funded 

Planning Month Year

Delivery Month Year

RAG Status

GREEN  / AMBER / RED

 

Plan

 

 

Dependencies

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

  

Project Code: CSG001 (AP number: AP23-011)

Project Title: Information Management for Health and Safety

Category: Compliance

Milestones

 

Target dateTitle
09-Aug-2013End of maintenance iteration
23-Aug-2013Closure
 

RAG Status: GREEN  

Report by Dawn Nicholls for July 2013 

Achievements this period

  • Release 1 went live on 10th July, which has allowed Health & Safety Dep't to start setting up master data
  • Release 2 completed 26th July and was passed to Health & Safety Dep't for testing
  • User testing feedback received from MRC and Biological Sciences

Issues

  • Developer resource has been difficult to secure due to departmental absences and recruitment activity.  This has impacted progress with both RETAIN and BOXI development.  As a result development is now going to extend into August.  Revised milestone dates are shown below.

Next steps

 

 Full details can be seen in the Project Journal

 

Section Four: Closed or Withdrawn Projects

  

Project InfoProject Managers Commentary

  

Project Code (AP Number)

Project Title

 

Discretionary/Compliance/Funded 

Report by [PM] 

This project was closed/withdrawn on dd-mmm-yy

[for closures] Please see the Completion Report / Closure Review for further information [include link]. 

[for withdrawn] Please see the PRICCL log for further details [include link].

 

 

Section Five: New Approved Projects from 13/14 Annual Plan

Any projects that were approved in previous annual planning rounds and have been postponed to start in 13/14 will be listed under section 2: Projects Not Started. Projects started in 12/13 but which will carry over to 13/14 are listed under section 3: In Progress.

  

Project InfoProject Managers Commentary

 AP34

Accident and Incident Reporting for Health and Safety

Compliance

Planning -

Delivery -

 

RAG Status

 

 

 Plan

 

Dependencies

 

 

Documentation

Not available.