Report for November 2020
- Report Date
- November 2020
Report compiled by Emma McNab
Section One: Programme Commentary, RAG and Resources Update


Forward Look





The Programme is continuing through the challenges presented by the current Covid-19 situation. There are 2 projects in progress and 1 yet to be started this year.
Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|
|
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||
|
CSG015 Risk Management System Procurement Milestones
RAG Status Amber |
|
||||
|
CSG017 IRM Intellectual Property (IP) Team Onboarding Milestones
RAG Status: AMBER
|
|
||||
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |