Report for February 2021
- Report Date
- February 2021
Report compiled by Emma McNab
Section One: Programme Commentary, RAG and Resources Update
Forward Look
The Programme is continuing through the challenges presented by the current Covid-19 situation. There are 2 projects in progress and 1 yet to be started this year.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
|
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||
CSG015 Risk Management System Procurement Milestones
RAG Status Amber |
Achievements in Last PeriodIssues:Next Steps: |
||||
CSG018 IRM Onboarding - Business School Industry Activity Milestones
|
Report by Andy Stewart for February 2021 Achievements in Last Period:Issues:Next Steps: |
||||
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
CSG017 IRM Intellectual Property (IP) Team Onboarding |