The Programme is continuing through the challenges presented by the current Covid-19 situation.  There are 2 projects in progress and 1 yet to be started this year.

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

 

 

 

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

CSG015

Risk Management System Procurement

Milestones 

 

Milestone Due Date
Project Closure 31 Mar 2021

 

RAG Status

Amber

Report by Andy Stewart for February 2021

Achievements in Last Period

Issues:

Next Steps:

CSG018 

IRM Onboarding - Business School Industry Activity

Milestones

Milestone Due Date
   

 

 

 

Report by Andy Stewart for February 2021

Achievements in Last Period:

Issues:

  •  

Next Steps:

   

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

CSG017

IRM Intellectual Property (IP) Team Onboarding

Closed 

 

AttachmentSize
Image icon csgnov.png76.46 KB
Image icon csgnov.png76.46 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No
Escalated to
Deputy CIO