Report for February 2022

Report Date
February 2022

Report compiled by Ben Armstrong 

Section One: Programme Commentary, RAG and Resources Update

 

Forward Look

Resources 

The Programme is continuing through the challenges presented by the current Covid-19 situation.  There are 2 projects in progress and 1 conpletedS.

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

N/A

 

None

 

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

CSG020

IRM Onboarding for UNICEF Collaborative

Milestones:

Stage Milestone Current Date 
Initiate WIS Approval 21-Jan-2022
Plan Planning Complete 25-Feb-2022
Execute Analysis and Design Complete 31-Mar-2022
Execute IRM Cab Agreement 31-Mar-2022
Execute Sandbox Environment Available 05-Apr-2022
Execute Complete Data Migration Test/Checks 15-Apr-2022
Execute User Acceptance Complete 29-Apr-2022
Execute Users Trained 12-May-2022
Deliver Data Migration/IRM Config live 27-May-2022
Deliver Handover to Support 03-Jun-2022
Close Project Closure 10-Jun-2022

RAG Status

Green 

Report by Gail Redford for February 2022

Achievements this Period

  • Project Brief complete(draft)
  • Resource estimating ongoing, just need final estimates for EI Technical Lead Resource

Issues 

  • None 

Next Steps 

  • Project Brief approval by Project Team
  • Complete Planning Stage

 

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

CSG017

IRM Intellectual Property (IP) Team Onboarding

Closed 

CSG019

IRM Onboarding for Social Responsibility and Sustainability

Closed
Programme Status
Has formal escalation taken place?
No