Report for April 2022

Report Date
April 2022

Report compiled by Ben Armstrong 

Section One: Programme Commentary, RAG and Resources Update

 

Forward Look

Resources 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

N/A

 

None

 

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

CSG020

IRM Onboarding for UNICEF Collaborative

Milestones:

Data Migration/IRM config live 27/5

Handover to support 3/6

Project closure 10/6 

 

RAG Status: Amber 

 

Report by Gail Redford for April 2022

Achievements this Period 

  • The initial Design completed 14/4/22
  • IRM Cab Agreement(Architecture and Service Management) completed 14/4/22.
  • Sandbox environment available  21/4/22

Issues 

  • no issues 

Next Steps 

  • The next key milestone is "Complete data migration test/checks".   This is later than planned,  with the first migration run completing by 12th May(the final data migration is planned to complete 27th May)

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

CSG017

IRM Intellectual Property (IP) Team Onboarding

Closed 

CSG019

IRM Onboarding for Social Responsibility and Sustainability

Closed
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No