Report for June 2022

Report Date
June 2022

Section One: Programme Commentary, RAG and Resources Update

 

Forward Look

Resources 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

N/A

 

None

 

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

CSG020

IRM Onboarding for UNICEF Collaborative

Milestones:

Milestone Due Date
Project Closure 14-Jul-2022

 

RAG Status: 

GREEN

Report by Gail Redford for June 2022

Achievements this Period 

  • MS  COMPLETE DATA MIGRATION TEST/CHECK  - completed as planned by 17 Jun 
  • USER ACCEPTANCE  MS completed as planned by 17 Jun
  • The DATA MIGRATION/IRM CONFIG LIVE MS  completed by 20 Jun
  • New users added to the IRM 20 Jun
  • Following the live config, the Business Lead(Fraser)did identify some additional data to be migrated and that was completed immediately. 
  • Handover to Support 30 Jun
  • Approval to close the project  confirmed by Alex Hutchison, Fraser Macdonald, Alasdair Macleod(Alan Hughes) and Jason Murphy(24 Jun).

Issues 

  • No new issues 

Next Steps 

  • Project closure report approval - still three approvers to follow up with. 
  • Target Apps Review 7th or 14th Jul for formal closure.

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

CSG017

IRM Intellectual Property (IP) Team Onboarding

Closed 

CSG019

IRM Onboarding for Social Responsibility and Sustainability

Closed
AttachmentSize
Image icon 202206_rag-othcsg.png85.62 KB
Image icon 202206_resources-othcsg.png41.68 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No