Report for August 2023

Report Date
August 2023

Report by Muriel Mewissen for Rick Arnautovic (Portfolio Owner) and CAHSS Programme Stakeholders.

Section One: Programme Commentary, RAG and Resources Update

The new 23/24 session starts with three ongoing projects. All are reporting an AMBER status due to delays and budgets to be confirmed. In addition, an with low resource availability in Project Services that is impacting the programme delivery has been recorded at the programme level. 

The status of the programme is set to AMBER.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - August 2023

 

Programme Resource to end of August 2023

Note that the programme budget for session 23/24 is not yet finalised.

 

Section Two: Projects Not Started

Project Info Core Funding Budget Allocation

Two additional projects will be started this session:

  1. HSS043 Online Survey Tool Requirements
  2. HSS044 Business School IRM On Boarding

CAHSS has 150 ring fenced days in 23/24. The following allocations have been made:

Ring Fence:

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

HSS040 ECA MiniPortfolio Procurement and Implementation

 

Milestones

Title Target Date
Deliver UG mini-portfolio solution for ECA UG programmes 31-Jul-2023
Closure 31-Aug-2023
 
RAG Status 

AMBER

Report by Sheona Chalmers for August 2023

Achievements this period

  • The integration between the student system and SMA has been successfully system tested end to end.
  • Project Board has been recommended that the fall back to ColdFusion is no longer required.
  • Integration design documentation has been prepared.
  • SMA configured for ECA programmes.
  • Support arrangements are in development.

Issues

  • Due to the time and effort  to develop and test the integration and configure SMA, a revised timeline and estimate are needed  to complete this project.  An estimate has been prepared and project milestones re-planned.  These need to be approved by the programme manager, budget holder and project sponsor.

  • SMA UoE custom email address.  The university has set up a no reply custom email address, however due to a technical issue the custom email address set up defaults to a SMA setting. Supplier is aware and has a fix for this issue, however we don't currently have a timescale for resolution.  We are currently exploring other options to address.

Next Steps

  • Complete configuration documentation for portfolio submission portal.
  • Plan and conduct user acceptance testing and manage defects.
  • Change control  for revised budget, timeline and milestones approved.
  • Support arrangements developed including early life and key milestone support.
  • EQIA approved.
  • As the current project manager is leaving, they will collate lessons learned and produce a draft closure report for hand over to the programme manager.

HSS041 Coordinating ISG Services for EFI Launch

 

Milestones - formal change control to be completed

Milestone Due Date
Printers installation completed - phase 1 05-Sep-2023
ECA link completed 08-Sep-2023
Door access control completed 15-Sep-2023
Delivery Complete (MAJOR) 15-Sep-2023
Networking for EFI opening 15-Sep-2023
AV for EFI opening 15-Sep-2023
Delivery review 06-Oct-2023
Project Closure (MAJOR) 27-Oct-2023
RAG Status 

AMBER

Report by Susan Ridder-Patrick for August 2023

Achievements this period

  • Door cards readers received from supplier and installed
  • Door access clearances provided by EFI and input
  • All AV physical installs have been completed
  • Network work completed in phase 1 part of building (outside of missing test results)
  • ECA resilient link work underway
  • Support arrangements for EFI pahse 1 drafted and out for review/agreement

Issue

  • Missing ~300 test results from BBK which is preventing completion of all network work in phase 1 building
  • Milestones to be formally changed

Next Steps

  • Printers being installed on 5th September
  • Complete ECA resilient link
  • Complete snagging of doors with BBK
  • Complete snagging and commissioning of AV equipment
  • Assess and complete any work once missing test results received
  • Complete agreement of support arrangements for phase 1

HSS042 Peace Agreements Database - Continous Improvements 22/23

 

Milestones

Title Target date
Launch new site 05-Sep-2023
Handover to Production 29-Sep-2023
Bundle #1 13-Oct-2023
Bundle #2 10-Nov-2023
Deliver improvements sign-off 17-Nov-2023
Close 30-Nov-2023
 
RAG Status 

AMBER

Report by Chantal Reilly for August 2023

Achievements this period

  • Tracker developments complete
  • Decision to continue project and deliver improvements while contractor available rather than close

Issues

  • Currently working out how many days will be in this project and how many in new project and will complete budget change as required.

Next Steps

  • Launch new site
  • Re-prioritize developments
  • Start work on next bundle

HSS043 Online Survey Tool Requirements

 

Milestones

Title Target Date
Initiation 04-Sep-2023
Planning 16-Oct-2023
Delivery 21-Dec-2023
Closure 26-Jan-2024
 
RAG Status 

AMBER

Report by Muriel Mewissen for August 2023

Achievements this period

  • PM & BA resources identified

Issues

  • Project was due to start in 2022/23 but due to lack of resources, this project will only start in September.

Next Steps

  • Initiate the project.

 

Section Four: Closed Projects

Project Info Project Manager's Commentary

N/A

No project has been closed yet this year.

Section Five: Programme Meeting Minutes

Date Comments
18 August 2023 Programme Review for August 2023
13 July 2023 Programme Review for July 2023
16 June 2023 Programme Review for June 2023
11 May 2023 Programme Review for May 2023
13 April 2023 Programme Review for April 2023
16 March 2023 Programme Review for March 2023
9 February 2023 Programme Review for February 2023
12 January 2023 Programme Review for January 2023
8 December 2022 Programme Review for December 2022
17 November 2022 Programme Review for November 2022
20 October 2022 Programme Review for October 2022
14 September 2022 Programme Review for September 2022
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Documentation

Not available.