Report for September 2023

Report Date
September 2023

Report by Muriel Mewissen for Rick Arnautovic (Portfolio Owner) and CAHSS Programme Stakeholders.

Section One: Programme Commentary, RAG and Resources Update

During September, a new project was started:

The EFI building early opening for Phase 1 took place, HSS041 Coordinating ISG Services for EFI Launch will now move to closure and the follow up project will be started.

Two projects are reporting an AMBER status while their milestones and budgets are under review:

The low resource availability in Project Services that is impacting the programme delivery contimues to delay the start of HSS044 Business School IRM On Boarding

The status of the programme is set to AMBER.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - Setember 2023

 

Programme Resource to end of September 2023

Note that the programme budget for session 23/24 is not yet finalised.

 

Section Two: Projects Not Started

Project Info Core Funding Budget Allocation

One additional project will be started this session:

  1. HSS044 Business School IRM On Boarding

CAHSS has 150 ring fenced days in 23/24. The following allocations have been made:

Ring Fence:

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

HSS040 ECA MiniPortfolio Procurement and Implementation

 

Milestones

Title Target Date
Deliver UG mini-portfolio solution for ECA UG programmes 31-Jul-2023
Closure 31-Aug-2023
 
RAG Status 

AMBER

Report by Sheona Chalmers for September 2023

Achievements this period

  • Project Board has agreed that the fall back to ColdFusion is no longer required and to proceed with the SMA solution, see Decision 23.
  • Configuration documentation for portfolio submission portal completed
  • User acceptance testing planned
  • Change control for revised budget, timeline and milestones drafted
  • Support arrangements developed including early life and key milestone support
  • Project team asked to document lessons learned for project closure report
  • Project closure report started

Issues

  • Due to the time and effort  to develop and test the integration and configure Survey Monkey Apply, a revised timeline and estimate have been prepared and project milestones re-planned, see Issue 19.

  • Ongoing issue with the University preferred no reply custom email address which is not displayed as expected. A technical solution has been identified and will be tested next week.

  • As the current project manager left at the end of September this project has been handed over to the programme manager, see Change 24.

Next Steps

  • Conduct user acceptance testing and manage priority defects
  • EQIA approval
  • Solution move to LIVE

HSS041 Coordinating ISG Services for EFI Launch

 

Milestones - formal milestone changes to me completed

Milestone Due Date
ECA link completed 08-Sep-2023
Delivery review 06-Oct-2023
Project Closure (MAJOR) 27-Oct-2023
RAG Status 

GREEN

Report by Susan Ridder-Patrick for September 2023

Achievements this period

  • Completion of snagging and commissioing of AV equipment ready for teaching
  • Completion of work on door access
  • Printers installed in phase 1
  • ECA resilient link completed (flip-over to be tested)
  • Clarity provided from BBK on majority of missing test results

Issue

  • Missing ~50 test results from BBK. BBK advised that Cat6a cables that were over 90m have not been installed. ITI have instucted AtkinsRealis (was F&G) that this work is to be completed.
  • Milestones to be formally changed
  • Estates have not completed key suiting for phase 1 due to delay with BBK. This has support implications as ITI CIS do not have normal 24x7 access.
  • Establishing status of all WAPs still being worked on
  • Problem with AVoIP has required change from multicasting to Unicast - to be worked on by LST and Network teams

Next Steps

  • Assess and complete any work once missing test results received
  • Test flip-over to ECA resilient link
  • Complete establishing status of all WAPs in phase 1
  • Obtain keys and clarity of support access for phase 1 part of building
  • Complete agreement of support arrangements for phase 1
  • Planning for phase 2 to begin

HSS042 Peace Agreements Database - Continous Improvements 22/23

 

Milestones

Title Target date
Handover to Production 27-Oct-2023
Deliver improvements sign-off 27-Oct-2023
Close 10-Nov-2023
 
RAG Status 

AMBER

Report by Chantal Reilly for September 2023

Achievements this period

  • Launched new site
  • Developments toward turning php off continue
  • SDD created
  • Discussions on development priorities begun
  • Discussions on production handover begun

Issues

  • Currently working out how many days will be in this project and how many in new project and will complete budget change as required.

Next Steps

  • Plan handover to Production
  • Update documentation for handover
  • Continue developments with a view to turning off php site
  • Align Jira with new development priorities

HSS043 Online Survey Tool Requirements

 

Milestones

Title Target Date
Planning 16-Oct-2023
Delivery 21-Dec-2023
Closure 26-Jan-2024
 
RAG Status 

GREEN

Report by Susan Ridder-Patrick for September 2023

 

This is a secure project and only those with access will be able to review the September project report.

HSS044 Business School IRM On Boarding

Milestones

 

RAG Status 

RED

Report by Muriel Mewissen for September 2023

Achievements this period

  • None

Issues

  • Project was due to start in 2022/23 but due to lack of resources, this project will only start in October with Service Management staff acting as PM.

Next Steps

  • Initiate the project.

 

Section Four: Closed Projects

Project Info Project Manager's Commentary

N/A

No project has been closed yet this year.

Section Five: Programme Meeting Minutes

Date Comments
29 September 2023 Programme Review for September 2023
18 August 2023 Programme Review for August 2023
13 July 2023 Programme Review for July 2023
16 June 2023 Programme Review for June 2023
11 May 2023 Programme Review for May 2023
13 April 2023 Programme Review for April 2023
16 March 2023 Programme Review for March 2023
9 February 2023 Programme Review for February 2023
12 January 2023 Programme Review for January 2023
8 December 2022 Programme Review for December 2022
17 November 2022 Programme Review for November 2022
20 October 2022 Programme Review for October 2022
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Documentation

Not available.