Report for October 2023
- Report Date
- October 2023
Report by Muriel Mewissen for Rick Arnautovic (Portfolio Owner) and CAHSS Programme Stakeholders.
Section One: Programme Commentary, RAG and Resources Update
During October, a new project was started:
The remaining projects in the programme are reporting either a RED RAG status:
- HSS040 ECA MiniPortfolio Procurement and Implementation - Fix and new request needed to be implemented following UAT and user training are impacting the very tight schedule for delivery.
- HSS042 Peace Agreements Database - Continous Improvements 22/23 - Changes in resources meant the project is extended but there is no PM currently available.
or an AMBER RAG status because of low stakeholder availability.
The low resource availability in Project Services as a HIGH impacting the programme delivery.
The status of the programme is set to RED.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - October 2023
Programme Resource to end of October 2023
Note that the programme budget for session 23/24 is not yet finalised.
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Possible areas of work to be started this session:
|
CAHSS has 150 ring fenced days in 23/24. The following allocations have been made: Ring Fence:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||
HSS040 ECA MiniPortfolio Procurement and Implementation
RAG StatusRED |
Report by Muriel for October 2023
This is a secure project and only those with access will be able to review the October project report.
|
||||||||||||||||||||||||||
HSS041 Coordinating ISG Services for EFI Launch
Milestones - formal milestone changes to me completed
RAG StatusAMBER |
Report by Susan Ridder-Patrick for October 2023Achievements this period
Issue
Next Steps
|
||||||||||||||||||||||||||
HSS042 Peace Agreements Database - Continous Improvements 22/23
RAG StatusRED |
Report by Chantal Reilly for October 2023Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||
HSS043 Online Survey Tool Requirements
RAG StatusAMBER |
Report by Susan Ridder-Patrick for October 2023
This is a secure project and only those with access will be able to review the October project report. |
||||||||||||||||||||||||||
HSS044 Business School IRM On Boarding
RAG StatusGREEN |
Report by Catherine Hetherington for October 2023Achievements this period
Issues
Next Steps
|
Section Four: Closed Projects
Project Info | Project Manager's Commentary |
---|---|
N/A |
No project has been closed yet this year. |
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
29 September 2023 | Programme Review for September 2023 |
18 August 2023 | Programme Review for August 2023 |
13 July 2023 | Programme Review for July 2023 |
16 June 2023 | Programme Review for June 2023 |
11 May 2023 | Programme Review for May 2023 |
13 April 2023 | Programme Review for April 2023 |
16 March 2023 | Programme Review for March 2023 |
9 February 2023 | Programme Review for February 2023 |
12 January 2023 | Programme Review for January 2023 |
8 December 2022 | Programme Review for December 2022 |
17 November 2022 | Programme Review for November 2022 |