Report for January 2024
- Report Date
- January 2024
Report by Muriel Mewissen for Rick Arnautovic (Portfolio Owner) and CAHSS Programme Stakeholders.
Section One: Programme Commentary, RAG and Resources Update
During January, a new project was added to the programme and initiated:
- HSS045 ISG Services for EFI Launch - Phase 2 to carry on the next phase of work on EFI with Phased 1 completed in HSS041 Coordinating ISG Services for EFI Launch
Two projects are AMBER:
-
HSS040 ECA MiniPortfolio Procurement and Implementation where the timeline and budget need to be extended to support additional development to address issues identified post Go LIVE.
-
HSS045 ISG Services for EFI Launch - Phase 2 where the building contractor is behind schedule and this will mean less time for the ISG teams to do their work on site.
The status of the programme is set to AMBER.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - January 2024
Programme Resource to end of January 2024
Note that the programme budget is now finalised and is set to 426 days, see 2023/24 - Mid-Year Programme Budget Review.
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Possible areas of work to be started this session:
|
CAHSS has 150 ring fenced days in 23/24. The following allocations have been made: Ring Fence:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
HSS040 ECA MiniPortfolio Procurement and Implementation
RAG StatusAMBER |
Report by Muriel Mewissen for January 2024
This is a secure project and only those with access will be able to review the January project report.
|
||||||||
HSS042 Peace Agreements Database - Continous Improvements 22/23
RAG StatusGREEN |
Report by Alan Donald for January 2024Achievements this period
Issues
Next steps
|
||||||||
HSS043 Online Survey Tool Requirements
RAG StatusGREEN |
Report by Susan Ridder-Patrick for January 2024
This is a secure project and only those with access will be able to review the January project report. |
||||||||
HSS044 Business School IRM On Boarding
RAG StatusClosed |
Report by Sue Woodger for January 2024Achievements this period
Next Steps
|
||||||||
HSS045 ISG Services for EFI Launch - Phase 2
RAG StatusAMBER |
Report by Susan Ridder-Patrick for January 2024Achievements this period
Issues
Next Steps
|
Section Four: Closed Projects
Project Info | Project Manager's Commentary |
---|---|
HSS044 Business School IRM On Boarding | This project was started in October 2023 and was closed on the 11 January 2024. The Closure Report is available to view. |
This project was started in March 2023 and was closed on the 15 December 2023. The Closure Report is available to view. |
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
16 January 2024 | Programme Review for December 2023 & January 2024 |
15 November 2023 | Programme Review for November 2023 |
29 September 2023 | Programme Review for September 2023 |
18 August 2023 | Programme Review for August 2023 |
13 July 2023 | Programme Review for July 2023 |
16 June 2023 | Programme Review for June 2023 |
11 May 2023 | Programme Review for May 2023 |
13 April 2023 | Programme Review for April 2023 |
16 March 2023 | Programme Review for March 2023 |
9 February 2023 | Programme Review for February 2023 |