Report for January 2024

Report Date
January 2024

Report by Muriel Mewissen for Rick Arnautovic (Portfolio Owner) and CAHSS Programme Stakeholders.

Section One: Programme Commentary, RAG and Resources Update

During January, a new project was added to the programme and initiated:

Two projects are AMBER:

The status of the programme is set to AMBER.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - January 2024

 

Programme Resource to end of January 2024

Note that the programme budget is now finalised and is set to 426 days, see 2023/24 - Mid-Year Programme Budget Review.

 

Section Two: Projects Not Started

Project Info Core Funding Budget Allocation

Possible areas of work to be started this session:

  1. Support for renewal of the WAM supplier contract

CAHSS has 150 ring fenced days in 23/24. The following allocations have been made:

Ring Fence:

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

HSS040 ECA MiniPortfolio Procurement and Implementation

 

Milestones

Title Target Date
Deliver UG mini-portfolio solution for ECA UG programmes 07-Feb-2024
Closure 15-Mar-2024
 
RAG Status 

AMBER

Report by Muriel Mewissen for January 2024

 

This is a secure project and only those with access will be able to review the January project report.

 

HSS042 Peace Agreements Database - Continous Improvements 22/23

 

Milestones

Title Target date
Handover to Production 01-Mar-2024
Deliver improvements sign-off 01-Mar-2024
Close 29-Mar-2024
 
RAG Status 

GREEN

Report by Alan Donald for January 2024

Achievements this period

  • Rates for 23/24 have been confirmed by PMO.
  • New PM taking over Project
  • Software Dev resource confirmed
  • New deployments ready for live
    • Final data import from Peace Agreements PHP site signed off
    • Researchers in PeaceRep team entering data into new platform in TEST as part of UAT
    • Update ready for LIVE site to prepare for the Tracker subsite launch in February

Issues

  • The Project is extended to complete this phase of work. The milestones and budget need to be confirmed.

Next steps

  • Implement Jira organisation changes 
  • Handover to Production
  • Update documentation for handover
  • Continue developments with a view to turning off php site

HSS043 Online Survey Tool Requirements

 

Milestones

Milestone Due Date
Project Delivery (MAJOR) 09-Feb-2024
Completion of Options Appraisal document 09-Feb-2024
Project Closure (MAJOR) 29-Feb-2024
 
RAG Status 

GREEN

Report by Susan Ridder-Patrick for January 2024

 

This is a secure project and only those with access will be able to review the January project report.

HSS044 Business School IRM On Boarding

 

Milestones

Title Target Date
Project Closure 12-Jan-2024
 
RAG Status 

Closed

Report by Sue Woodger for January 2024

Achievements this period

Next Steps

  • None. Project Closed.

 HSS045 ISG Services for EFI Launch - Phase 2

 

Milestones

Title Target Date
End of Planning - Major 09-Feb-2024
Delivery - Major 15-Apr-2024
Project Closure - Major 20-Dec-2024
 
RAG Status 

AMBER

Report by Susan Ridder-Patrick for January 2024

Achievements this period

  • Project initiated
  • Project brief being drafted
  • Room booking workshop held
  • ITI CIS have progressed work

Issues

  • BBK delay meant ITI CIS could not start as planned on 8th January. However, as phase 2 is in a better state than phase 1 was, the team are making good progress
  • Events Space work potentially delayed to end of March which will put pressure on ISG teams to complete
  • Confirmed Tenant requirements not available until w/c 12th February

Next Steps

  • Complete project brief
  • External tenant requirements to be confirmed
  • Work through each ISG service to confirm how these will be delivered to all users in the EFI building

 

Section Four: Closed Projects

Project Info Project Manager's Commentary
HSS044 Business School IRM On Boarding This project was started in October 2023 and was closed on the 11 January 2024. The Closure Report is available to view.

HSS041 Coordinating ISG Services for EFI Launch

This project was started in March 2023 and was closed on the 15 December 2023. The Closure Report is available to view.

 

Section Five: Programme Meeting Minutes

Date Comments
16 January 2024 Programme Review for December 2023 & January 2024
15 November 2023 Programme Review for November 2023
29 September 2023 Programme Review for September 2023
18 August 2023 Programme Review for August 2023
13 July 2023 Programme Review for July 2023
16 June 2023 Programme Review for June 2023
11 May 2023 Programme Review for May 2023
13 April 2023 Programme Review for April 2023
16 March 2023 Programme Review for March 2023
9 February 2023 Programme Review for February 2023
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Documentation

Not available.