Report for February 2024
- Report Date
- February 2024
Report by Muriel Mewissen for Rick Arnautovic (Portfolio Owner) and CAHSS Programme Stakeholders.
Section One: Programme Commentary, RAG and Resources Update
During February, a project was successfully delivered and closed:
- HSS043 Online Survey Tool Requirements. The Closure Report is available to view.
HSS040 ECA MiniPortfolio Procurement and Implementation is reporting a RED RAG due to several issues post Go-LIVE that have impacted the submission process and that require to be addressed. This has caused additional work for all teams involved, and impact on timeline and budget.
HSS045 ISG Services for EFI Launch - Phase 2 continue to report an AMBER RAG due to the building contractor delays which means less time will be available for the ISG teams to do their work on site.
The status of the programme is set to AMBER.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - February 2024
Programme Resource to end of February 2024
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Possible areas of work to be started this session:
|
CAHSS has 150 ring fenced days in 23/24. The following allocations have been made: Ring Fence:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
HSS040 ECA MiniPortfolio Procurement and Implementation
RAG StatusRED |
Report by Muriel Mewissen for February 2024
This is a secure project and only those with access will be able to review the February project report.
|
||||||||
HSS042 Peace Agreements Database - Continous Improvements 22/23
RAG StatusGREEN |
Report by Alan Donald for February 2024
Achievements this period
Issues
Next steps
|
||||||||
HSS043 Online Survey Tool Requirements
RAG StatusClosed |
Report by Susan Ridder-Patrick for February 2024
This is a secure project and only those with access will be able to review the February project report.
|
||||||||
HSS045 ISG Services for EFI Launch - Phase 2
RAG StatusAMBER |
Report by Susan Ridder-Patrick for February 2024Achievements this period
Issues
Next Steps
|
Section Four: Closed Projects
Project Info | Project Manager's Commentary |
---|---|
HSS043 Online Survey Tool Requirements | This project was started in September 2023 and was closed on the 29 February 2024. The Closure Report is available to view. |
HSS044 Business School IRM On Boarding | This project was started in October 2023 and was closed on the 11 January 2024. The Closure Report is available to view. |
This project was started in March 2023 and was closed on the 15 December 2023. The Closure Report is available to view. |
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
13 February 2024 | Programme Review for February 2024 |
16 January 2024 | Programme Review for December 2023 & January 2024 |
15 November 2023 | Programme Review for November 2023 |
29 September 2023 | Programme Review for September 2023 |
18 August 2023 | Programme Review for August 2023 |
13 July 2023 | Programme Review for July 2023 |
16 June 2023 | Programme Review for June 2023 |
11 May 2023 | Programme Review for May 2023 |
13 April 2023 | Programme Review for April 2023 |
16 March 2023 | Programme Review for March 2023 |