Report for August 2024

Report Date
August 2024

During August, the FLAC Analysis Project initiation documents were pulled together and this will start in September

No projects are reporting a RED status

No project are reporting an AMBER status:

Four projects are reporting a GREEN status:

One project is in the process of being suspended as funding is not clear

The status of the programme is set to GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - August 2024

 

Programme Resource to end of August 2024

 

Section Two: Projects Not Started

Project Info Core Funding Budget Allocation

Possible areas of work to be started this session:

  1. FLAC Analysis Project
  2. Support for Targeting Communication

CAHSS has 150 ring fenced days in 24/25. The following allocations have been made:

Ring Fence:

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

ECA MiniPortfolio Procurement and Implementation (HSS040)

 

Milestones (under review)

Accept Start Remedial Changes UAT 09-Sep-2024
Close Closure - MAJOR MILESTONE 04-Oct-2024
 
RAG Status 

GREEN

Report by Alan Donald for August 2024

 

This is a secure project and only those with access will be able to review the June project report.

 

Peace Agreements Database - Continuous Improvements 22/23 (HSS042)

 

Milestones

Title Target Date
Close 06-Sep-2024
 
RAG Status 

GREEN

Report by Alan Donald for August 2024

 

Achievements this period

  • Fornightly team meetings continuing
  • Closure report shared with outgoing Programme Manager, Senior Supplier and Project Sponsor
  • Budget meetings arranged with Sponsor

Issues

  • The Project is extended to complete this phase of work. The milestones and budget need to be confirmed.
  • Production resource is limited. Releases will need to planned around this - John Allison taking up with Production
  • Budget was confirmed to the end of March - needs to be adjusted taking the extension into account

Next steps

  • Close Project, start new Project for 24/25
  • Update documentation for handover
  • Ongoing Amnesties DB work

 ISG Services for EFI Launch - Phase 2 (HSS045)

 

Milestones

Title Target Date
Complete requirements gathering for EFI (DDI) partners and members 28-Jun-2024
Room booking design 26-Jul-2024
Desk Booking design 26-Jul-2024
Helpline & BAU Support model(s) agreed 09-Aug-2024
Full ECA resilient link test 01-Sep-2024
Reinstall equipment after Edinburgh Book Festival 06-Sep-2024
Confirm readiness for start of semester (MAJOR) 06-Sep-2024
Provision of services for EFI (DDI) tenants (MAJOR) 30-Sep-2024
Delivery review 15-Nov-2024
Project Closure (MAJOR) 20-Dec-2024
 
RAG Status 

GREEN

Report by Susan Ridder-Patrick for August 2024

Achievements this period

  • Confirmation received from Estates/Atkins Realis that remaining WAPs will be installed by BBK
  • Successful Book Festival event for the first time in EFI
  • LST progressing with re-installation of all teaching equipment ready for start of freshers' week

Issues

  • Billing processes in Hubs walkthrough identified gap in planned process which TTU031 EventMap Booker project team is reviewing
  • Scheduling of remaining WAPs installation to be agreed
  • No confirmed date from ITI CIS yet for the switch replacement for the resilient link

Next Steps

  • Milestones to be reviewed and closed by team
  • DDI Requirements sign-off to be confirmed as completed
  • Complete DDI design work/agree what options are if Hubs choose to make changes in the future
  • Complete final update on the project's control sheet for each space in EFI, including support arrangements
  • Continue with Eventmap pilot
  • Replace switch and test resilient link

OCS Upgrade (HSS046)

 

Milestones

 

Milestone

Due Date

Project Brief

30 Aug 2024

Creation of TEST and LIVE Rocky servers

6 Sep 2024

TEST environment OCS upgrade completed

30 Sep 2024

LIVE environment OCS upgrade completed

14 Oct 2024

Post deployment support

25 Oct 2024

Close

31 Oct 2024

These are project brief milestones - still to be approved by AppsReview

 

 

RAG Status 

GREEN

Report by Sue Woodger for August 2024

Achievements this period

  • Awaiting final sign off of project brief – will be submitted to Apps Review by 6 Sept 24
  • Supplier agreed to work and timescales

Issues

  • No issues this month

Next Steps

  • Meeting to discuss design and build with Production, DevTech and Supplier
  • Work to begin on building new servers

 

 

 

Section Four: Closed Projects

 

Section Five: Programme Meeting Minutes

Date Comments
15 September 2024 CAHSS Programme Review Meeting - August 2024
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.