Report for December 2024
- Report Date
- December 2024
During December,
No projects are reporting a RED status
Three projects are reporting an AMBER status:
- ECA MiniPortfolio Procurement and Implementation (HSS040) - Closure Milestone to be moved to bring it back into line as project closes, will return to Green following this change.
- OCS Upgrade | Project Management - Test milestone missed - Discussions ongoing with supplier.
- Free Legal Advice Centre (FLAC) - File Store Analysis | Project Management - Milestones missed due to time delay in completing the As-Is - New milestone dates to be approved
Two projects are reporting a GREEN status:
Sponsor Funded
- REDCap Installation Project (HSS047) - - Restarted following suspension
- Peace Agreements Database – Continuous Improvements 24/25 (HSS048)
The status of the programme is set to GREEN.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - December 2024
Programme Resource to end of December 2024
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Possible areas of work to be started this session:
|
CAHSS has 150 ring fenced days in 24/25. The following allocations have been made: Ring Fence:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
ECA MiniPortfolio Procurement and Implementation (HSS040)
Milestones (under review)
RAG StatusGREEN |
Report by Alan Donald for November 2024
This is a secure project and only those with access will be able to review the November project report.
|
||||||||||
Peace Agreements Database - Continuous Improvements 22/23 (HSS042)
RAG StatusGREEN |
Report by Alan Donald for November 2024
Achievements this period
Issues
Next steps
|
||||||||||
ISG Services for EFI Launch - Phase 2 (HSS045)
RAG StatusGREEN |
Report by Susan Ridder-Patrick for November 2024Achievements this period
Issues
Next Steps
|
||||||||||
These are to be revised
RAG StatusAMBER |
Report by Sue Woodger for December 2024Achievements in last period
Issues
Next Steps
|
||||||||||
REDCap Installation Project (HSS047)
MilestonesTBC RAG StatusGREEN
|
Report by Chris Konczak for December 2024Achievements in Last Period
Issues
Next Steps
|
||||||||||
Peace Agreements Database – Continuous Improvements 24/25 (HSS048)
MilestonesTBC RAG StatusGREEN |
Report by Alan Donald for December 2024Achievements this period
Issues
Next steps
|
||||||||||
Free Legal Advice Centre (FLAC) - File Store Analysis (HSS049)These are to be revised
RAG StatusAMBER |
Report by Sue Woodger for December 2024Achievements in last period
Issues
Next Steps
|
Section Four: Closed Projects
Peace Agreements Database - Continuous Improvements 22/23 |
ISG Services for EFI Launch - Phase 2 |
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
15 August 2024 | CAHSS Programme Review Meeting - August 2024 |
18 September 2024 | CAHSS Programme Review Meeting - September 2024 |
CAHSS Programme Review Meeting - October 2024 | |
CAHSS Programme Review Meeting - November 2024 |
Attachment | Size |
---|---|
![]() | 136.52 KB |
![]() | 74.73 KB |