Report for January 2025

Report Date
January 2025

 

During January,

No projects are reporting a RED status

One projects are reporting an AMBER status:

Four projects are reporting a GREEN status:

 

The status of the programme is set to GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - January 2025

 

Programme Resource to end of January 2025

 

Section Two: Projects Not Started

Project Info Core Funding Budget Allocation

Possible areas of work to be started this session:

  1. Support for Targeting Communication (Project start Jan25

CAHSS has 150 ring fenced days in 24/25. The following allocations have been made:

Ring Fence:

 

Section Three: Projects in Progress

ECA MiniPortfolio Procurement and Implementation  (HSS040)

Milestones

Close Closure - MAJOR MILESTONE 14-Feb-2025 31-Jan-2025 No

view

RAG Status

Green

Report by Alan Donald for January 2025

Achievements

  • Cycle open for submissions, business handling issues
  • Project Brief circulated to key stakeholders
  • Closure Milestone adjusted

Issues

  • Budget discussed with Project Sponsor

 

Next Steps

  • Complete Deployment Checklist
  • Update Closure Report based on feedback from key stakeholders
  • Close Project

OCS Upgrade (HSS046)

 

Milestones

These are to be revised

Milestone

Due Date

TEST environment OCS upgrade completed

13-Dec-2024

LIVE environment OCS upgrade completed

14-Jan-2025

Post Deployment support and DSOR

28-Jan-2025

Close

31-Jan-2025

 

 

RAG Status 

AMBER

Report by Sue Woodger for January 2025

Achievements in last period

  • Revised dates were agreed with the supplier with the TEST Environment upgrade due to be completed by the 31st Jan
  • Milestones revised and noted by Apps Review

Issues

  • DevTech and FactorFX will check changes made  and continue to investigate a couple of issues (ocsinventory-docker-image/unbuntu update and docker image timezone) holding up Test completion and a meeting will be arranged. Will include Euan Cameraon/David Outen so they can understand the system better.
  • 31st Jan milestone for upgrade of TEST Environment may have been missed, meaning the 3rd of Feb for TEST sign off is not achievable

Next Steps

  • Meeting with Supplier and DevTech. Sponsor also attending
  • Project Manager will revise the milestones
  • TEST environment completed
  • CAHSS to test the TEST environment
  • Work to begin on Live environment

Commentary:  Project is AMBER.

Description: The project is Amber due to Test milestone being missed. To confirm with DevTech and Supplier when this can be met

Impact: Milestones are affected

Plan: Supplier and DevTech to meet to confirm changes needed and Test build can recommence. PM to review once dates are confirmed

 

REDCap Installation Project (HSS047)

 

Milestones
Milestone Due Date
End of Planning 07-Feb-2025
TEST and LIVE infrastructure build complete    20-Feb-2025
Integration testing complete complete 28-Feb-2025
LIVE build complete 06-Mar-2025
DSOR 18-Mar-2025
Project Close 28-Mar-2025
RAG Status

GREEN

 

Report by Chris Konczak for January 2025

Achievements in Last Period

  • Project brief completed and is ready to circulate
  • Milestones and estimation completed
  • Resources assigned

Issues

  • Budget increase after review of the estimation noted inadequate project management time when the estimation was done pre-suspension. Increase from 26 days to 35 days.

Next Steps

  • Project brief to be signed off by project team and Apps Review
  • VM Servers to be ordered and setup
  • REDCap to be downloaded

 

Peace Agreements Database – Continuous Improvements 24/25  (HSS048)

 

Milestones
Stage Milestone Due Date  
Initiate Project Initiated 04-Oct-2024

view

Execute Fortnightly Sprints Start - MAJOR MILESTONE 31-Oct-2024

view

Execute New Senior Software Developer starts 18-Nov-2024

view

Execute Handover between Software Developers completed 29-Nov-2024

view

Initiate End of Planning - MAJOR MILESTONE 30-Jan-2025

view

Build New Staging Environment Completed 14-Feb-2025

view

Deliver Amensties DB Upgrade Completed & Decommissioning Started 28-Feb-2025

view

Deliver TAD and SDS Updated 21-Mar-2025

view

Deliver End of Final Delivery Sprint (MAJOR MILESTONE) 27-Mar-2025

view

Close Project Closure - MAJOR MILESTONE 31-Mar-2025

view

RAG Status

GREEN

Report by Alan Donald for January 2025

Achievements this period

  • Project Brief signed off
  • Project noted at Apps Review
  • Fortnightly sprints prioritised
  • Staging environment build underway
  • Python decommissioning process agreed with INF169 - not charged to project

Issues

  • Apps Review suggested a higher priority for project, to be discussed at next meeting

Next steps

  • Continue fortnightly meetings
  • Report budget position to Sponsor
  • Arrange meeting with Production
  • Complete Staging environment build.
Free Legal Advice Centre (FLAC) - File Store Analysis (HSS049)
 

These are to be revised

Milestone

Due Date

Delivery (Analysis) 

18/02/25

Close 21/02/25
RAG Status 

AMBER

Report by Sue Woodger for January 2025

Achievements in last period

  • Analysis is ongoing. However, the AS-IS this has taken much longer than anticipated
  • PM has started on the actual requirements based on information already collected
  • Milestones updated

Issues

  • AS-IS this has taken much longer than anticipated and was unable to be completed due to Christmas break
  • This has resulted in missed milestones and impending overspend. PM has spoken to Programme manager regarding this and will submit revised milestones and budget to Apps Review once agreed with sponsor

Next Steps

  • Complete the AS-IS
  • Complete TO-BE and requirements
  • Hold walkthrough
  • Sign off analysis

 

Section Four: Closed Projects

Peace Agreements Database - Continuous Improvements 22/23
ISG Services for EFI Launch - Phase 2

 ISG Services for EFI Launch - Phase 2 (HSS045)

Peace Agreements Database - Continuous Improvements 22/23 (HSS042)

Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.