Report for January 2025
- Report Date
- January 2025
During January,
No projects are reporting a RED status
One projects are reporting an AMBER status:
- OCS Upgrade | Project Management - Test milestone missed - Discussions ongoing with supplier.
Four projects are reporting a GREEN status:
- REDCap Installation Project (HSS047) - - Restarted following suspension
- Peace Agreements Database – Continuous Improvements 24/25 (HSS048)
- ECA MiniPortfolio Procurement and Implementation (HSS040) - Closure Milestone amended
- Free Legal Advice Centre (FLAC) - File Store Analysis | Project Management - Milestones amended
The status of the programme is set to GREEN.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - January 2025
Programme Resource to end of January 2025
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Possible areas of work to be started this session:
|
CAHSS has 150 ring fenced days in 24/25. The following allocations have been made: Ring Fence:
|
Section Three: Projects in Progress
ECA MiniPortfolio Procurement and Implementation (HSS040) Milestones
RAG Status Green |
Report by Alan Donald for January 2025 Achievements
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||
These are to be revised
RAG StatusAMBER |
Report by Sue Woodger for January 2025Achievements in last period
Issues
Next Steps
Commentary: Project is AMBER. Description: The project is Amber due to Test milestone being missed. To confirm with DevTech and Supplier when this can be met Impact: Milestones are affected Plan: Supplier and DevTech to meet to confirm changes needed and Test build can recommence. PM to review once dates are confirmed |
||||||||||||||||||||||||||||||||||||||||||||
REDCap Installation Project (HSS047)
Milestones
RAG StatusGREEN
|
Report by Chris Konczak for January 2025Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||
Peace Agreements Database – Continuous Improvements 24/25 (HSS048)
Milestones
RAG StatusGREEN |
Report by Alan Donald for January 2025Achievements this period
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||||||||
Free Legal Advice Centre (FLAC) - File Store Analysis (HSS049)These are to be revised
RAG StatusAMBER |
Report by Sue Woodger for January 2025Achievements in last period
Issues
Next Steps
|
Section Four: Closed Projects
Peace Agreements Database - Continuous Improvements 22/23 |
ISG Services for EFI Launch - Phase 2 |
ISG Services for EFI Launch - Phase 2 (HSS045)
Peace Agreements Database - Continuous Improvements 22/23 (HSS042)