Report for September 2018

Report Date
September 2018

Report by Muriel Mewissen for Fraser Muir (Portfolio Owner)

 

Section One: Programme Commentary, RAG and Resources Update

During September, work progressed well across all ongoing projects. The HSS020 CAHSS WAM Extended Pilot successfully completed and the project was close on the 28 September 2018. The Closure Report is available to view. All activities around WAM continue in HSS022 CAHSS WAM Deployment project.

One project was suspended: HSS024 Support for the Xerte pilot will now implement EASE authentication. This work is scheduled for October and the project is suspended until resources are available.

Two projects remain AMBER:

  • HSS015 School of Economics Job Study where a risk remains around the DWP granting permission to share data with University, and the external supplier has delayed the full application launch.
  • HSS023 Student Voice where part of the analysi had to be delayed to suit stakeholder availability.

All other projects have a GREEN status.

The overall status of the CAHSS programme is GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - September 2018

Programme Resource to end of September 2018

Section Two: Projects Not Started

Project Info Programme Manager's Commentary

The initiation of one further project has started in 17/18:

Proposed area for projects in 18/19:

  • Scottish Studies Digital Archive:
    • an initial meeting took place on 5 September 2018 which included representatitves of CAHSS, EDINA, Digital Library and Project Services, to assess the needs and secure resources to initiate the project. This work is urgent and expected to start in October 2018.
  • A joined project with CSE to extend work on lease standardisation done by MVM in MVM027 and MVM501 on Lease Standardisation.
  • Support for Edinburgh Future Institute
  • Support for Karen Howie, IT Manager for the School of  History, Classics and Archeology. 
  • Course and programme handbooks

CAHSS had a budget of 150 ring fenced days for 18/19 which has not been allocated yet.

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

HSS015

School of Economics Job Study

 

Milestones

Projected milestones - but still to be confirmed with project sponsor and programme manager

Target Date Title
22-Oct-18 Job Search 2 go live with API enabled
21-Dec-18 Data views
18-Jan-19 Closure

 

RAG Status

AMBER

Report by Andy Stewart for September 2018

Achievements in the Last Period

  • Ingeus have advised that Phase 3 development will commence in early November
  • Data Security
    • Discussions are now on-going between UoE, Ingeus and DWP to clarify data access
    • UoE are now being involved in the discussions with DWP
    • DWP to prepare an agreement that will require to be reviewed by UoE legal department
  • UoE testing has commenced briefly
  • Deployment Check List has been completed by technology Management
  • The scheduled Ingeus go-live (incorporating the control group only and API disabled) went live on 3rd September 2018
  • Commenced SDD and API vulnerabilities checks
  • Live infrastructure has been prepared

Issues

  • Data Security
    • Whilst progress is on-going with DWP, agreement has still to be reached
  • OLA updated, currently awaiting feedback from Fraser Muir 
  • UoE testing
    • This has not progressed as planned due to
      • a few technical issues have been encountered with user set-up and data transfer issues between Ingeus and UoE
      • lack of technical resource being supplied by Ingeus, who are now only supplying technical resource during the period of 4th to 9th October

Next Steps

  • Complete UAT as appropriate- scheduled to complete by 11th October
  • Complete SDD and API vulnerabilities checks - scheduled to complete by 8th October
  • Complete initial tests for the Live infrastructure
  • Complete OLA for IS Apps and the business user
  • DWP approval

RAG Commentary

Issue: Confirmation is still outstanding from the Department of Works and Pensions that UoE will be permitted to receive job study captured via the Ingeus workplace interface and in addition lack of technical resource from the supplier during the latest round of UAT.

 

HSS020

CAHSS WAM Extended Pilot

 

Milestones
Target Date Title
28-Sep-2018 Closure
 
RAG Status

CLOSED

Report by Geoff Cropley for September 2018

Achievements this period

  • Moray House remaining Institutes are now live. 
  • Project success criteria met and the project closed on 28 September.
  • The Closure Report is available to view.

Issues

  • None

Next Steps

  • None

HSS022

CAHSS WAM Deployment

 

Milestones
Target Date Title
14-Sep-2018 College of Medicine and Veterinary Medicine( CMVM)
28-Dec-2018 Centre for Edinburgh College of Art (ECA)
28-Dec-2018 School of Social and Political Science
28-Dec-2018 School of Business
28-Dec-2018 School of Economics
28-Dec-2018 Centre for Open Learning
31-Dec-2018 Closure
 
RAG Status

GREEN

Report by Geoff Cropley September 2018

Achievements in the Last Period

  • Moray House, all institutes, Law, LLC and HISS live. 
  • The WAM build models for Business School, Economics and SPS are complete with data gathering underway.  B
  • uilds for ECA and COL are in progress and is expect to complete by 31st October 2108.

Issues

  • None

Next Steps

  • Complete WAM build for ECA and COL.
  • Complete data gathering and commence UAT for Business School, Economics and SPS

 

HSS023

Student Voice

 
Milestones

Projected milestones - but still to be confirmed with project sponsor and programme manager

Target Date

Title

10-Oct-2018 Requirements Signed off
02-Nov-2018 Analysis Phase Completed
16-Nov-2018 Options Paper Signed-Off and Deliver Phase Completed
29-Nov-2018 Project Closure Completed
RAG Status

AMBER

Report by Ken Miller for September 2018

Achievements in the Last Period

  • BRD updated and Programme Rep scope clarified prior to v0.8 released for review.
  • Feedback received and BRD updated to version 0.9.
  • BA resource assigned to carry out Unitu and 3rd party investigation.
  • Review meeting held with project sponsor.

Issues

  • LTW resource required to investigate suitability of Learn against the signed off BRD.  Resource not available until October at the earliest.

Next Steps

  • Latest BRD document, v0.9 released for review.
  • Sign off As-is and BDR document.
  • Investigation of proposed options against requirements.

 

HSS024

Support for the Xerte pilot

 
Milestones

Agreed at WIS 14-Sep-2018:

Target Date Title
29-Oct-2018 Restart the Project
09-Nov-2018 Sign Off EASE Authentication
13-Nov-2018 Deploy EASE Authentication to LIVE
23-Nov-2018 Closure
 
RAG Status

SUSPENDED

 

Report by Richard Bailey for September 2018

Achievements in the Last Period

  • Additional budget was made available to provide EASE Authentication
  • Project re-planned and resource booked
  • Project suspended at WIS 14-Sep-2018

Issues

  • None  

Next Steps

  • Project currently suspended, planned to restart 29-Oct-2018
  • Update and complete TAD / CMDB entry
  • Finalise / agree the Operational Level Agreement (OLA)
  • Make script changes and apply EASE authentication (SSO) to Xerte 
  • Prepare Closure Report
  • Close the Project

 

HSS025

First Impressions - Digital Signage

 

Milestones
Target Date Title
28-Sep-2018 Design Standards, Use Cases and Content Types Definition Complete
22-Oct-2018 Digital Notice Boards & Signage Guidelines Complete
08-Nov-2018 Target Operating Model Definition Complete
23-Nov-2018 Digital Display Service Definition Complete
14-Dec-2018 Complete Design Templates
31-Jan-2019 Technology Options Paper Complete
14-Feb-2019 Closure
RAG Status

GREEN

Report by Geoff Cropley for September 2018

Achievements this period

  • Good progress has been made in identifying the various use cases from across the University.  This is required to be able to underpin user experience feedback to support user and business requirements gathering.
  • Communications & Marketing have been engaged to help develop digital display standards and guidelines.
  • An options analysis workshop was held to support data feeds from timetabling.  This is necessary as the current feed data format is a significant barrier to displaying room timetable information.  The outcome of the workshop was to request a new API.
  • The Current URL feed from timetabling is being assessed for continued use but with a new digital display template and content management application in line with EdGel design standards.
  • Proposed template has been designed for screens outside of meeting rooms.  This is the most common and well understood use case. The template is based on the Business School standard which has been usability and accessibility tested.

Issues

  • None

Next Steps

  • Continue with project delivery milestones.

 

HSS027

Hope Park Counselling Centre System Implementation

 

Milestones
Target Date Title
10-Oct-2018 Sprint 2 demo
24-Oct-2018 Sprint 3 demo
07-Nov-2018 Sprint 4 demo
30-Nov-2018 User Acceptance
25-Jan-2019 Training Delivery Block 1 (staff)
08-Feb-2019 Delivery (Deployment to LIVE) - soft launch
22-Feb-2019 Training Delivery Block 2 (students)
28-Feb-2019 Closure
RAG Status

GREEN

Report by Ben Armstrong for September 2018

Achievements this period

  • Signed off user stories and acceptance criteria required by supplier
  • Viewed Sprint 1 demo by supplier
  • Wrote test scripts for Sprint 1
  • Booked Development Technology resource for technical work

Issues

  • None noted

Next Steps

  • Technical Architecture Document and Domain Name request
  • Sprint 2 development
  • Sprint 2 demo - 11th October
  • Sprint 3 plan
  • Sprint 3 development
  • Test and implement EASE (single sign-on) integration

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
HSS020 CAHSS WAM Extended Pilot This project was started in September 2017 and was closed on the 28 September 2018. The Closure Report is available to view.

 

Section Five: Programme Risk Register

Risk RAG Comments
Risk 6: Possible change in PM for pilot and rollout of WAM projects GREEN Contract extension is planned to cover the end of the pilot and considered for the rollout.

 

Section Six: Programme Meeting Minutes

Date Comments
14 August 2018 Programme Review for June & July 2018 - meeting notes
15 June 2018 Programme Review for May 2018 - meeting notes
22 May 2018 Programme Review for April 2018 - meeting notes 
11 Apr 2018 Programme Review for March 2018 - meeting notes
14 Mar 2018 Programme Review for February 2018 - meeting notes
15 Feb 2018 Programme Review for December 2017 & January 2018 - meeting notes
9 Jan 2018 Programme Review for November 2017 - meeting notes
15 Nov 2017 Programme Review for October 2017 - meeting notes
11 Oct 2017 Programme Review for September 2017 - meeting notes
13 Sep 2017 Programme Review for August 2017 - meeting notes