Report for November 2019
- Report Date
- November 2019
Report by Muriel Mewissen for Fraser Muir (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
During November, HSS026 ECA Induction - Analysis and support for implementation of a school intranet site was successfully delivered. The Closure Report is now available.
HSS015 School of Economics Job Study remains RED while APM (formerly Ingeus) advise of the updated timeline for the remaining developments. A target date for these has been set to end of January 2020.
Two projects report an AMBER status:
- HSS027 Hope Park Counselling Centre System Implementation following delay in UAT and impact from the UCU Industrial Action - 25 November to 4 December 2020.
- HSS031 WAMS Business Embedding has been affected the BA resource on CAHSS project assigned to higher priority programme. A new BA is now in place but the project has been delayed and also due to the impact from the UCU Industrial Action - 25 November to 4 December 2020.
In addition non started project continued to be delayed because of the lack of resourcing:
- HSS032 Xerte Pilot - authorisation and business case is expected to start next month however the delay will impact the submission on the proposal based on the business case.
- HSS033 Centre for Open Learning - Business Process and Systems Review has been escalated because of EOL to the support of some underlying applications.
- Initial BA work was started for the Scottish Graduate School of Social Sciences (SGSSS)
Therefore, the status of the programme is set to AMBER.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - November 2019
Programme Resource to end of November 2019
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Proposed area for projects next year in session 19/20:
|
CAHSS had a budget of 150 ring fenced days for 19/20. The following allocations have been made:
This leaves another 38 days to be allocated. Some allocation are yet to be confirmed. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||
MilestonesThe following milestones are based on the following assumptions - none of which have been verified with the business partner
RAG StatusRED |
Report by Andy Stewart for November 2019Achievements in the Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
CAHSS WAM Deployment
Milestones
RAG StatusGREEN |
Report by Muriel Mewissen for November 2019Achievements in the Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
ECA Induction - Analysis and Development of a school intranet site
RAG StatusCLOSED |
Report by Ken Miller for November 2019Achievements
Next Steps
|
||||||||||||||||||||||||||||||
Hope Park Counselling Centre System Implementation
Milestones
RAG StatusAMBER |
Report by Andy Stewart for November 2019Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
School Programme Quality System (SPQS) Improvements
RAG StatusGREEN |
Report by Kevin Hone for November 2019Achievements in the Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
RAG StatusGREEN |
Report by Anne Mathison for November 2019Achievements in the Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
RAG StatusAMBER |
Report by Susan Ridder-Patrick for November 2019Achievements in the Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
Centre for Open Learning - Business Process and Systems Review
RAG StatusNOT STARTED - RED |
Report by Muriel Mewissen for November 2019Achievements in the Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
HSS026 ECA Induction - Analysis and support for implementation of a school intranet site | This project was started in October 2018 and was closed on the 22 November 2019. The Closure Report is available to view. |
HSS028 A Digital Archive for Scottish Studies - Appraisal & Strategy |
This project was started in November 2018 and was closed on the 18 October 2019. The Closure Report is available to view. |
Section Five: Programme Risk Register
Risk | RAG | Comments |
---|---|---|
Risk 8: Initiation of new projects in session 2019/20 may be delayed due to lack of resourcing | RED | New Project Services staff started on 4 Nov following successful recruitment. Recruitment for additional PMs is ongoing. Additional resource pressure has been created by a new issue, see PRICCL97 - BA resource on CAHSS project assigned to higher priority programme |
Section Six: Programme Meeting Minutes
Date | Comments |
---|---|
14 November 2019 | Programme Review for October 2019 - meeting notes |
28 October 2019 | Programme Review for September 2019 - meeting notes |
24 September 2019 | Programme Review for August 2019 - meeting notes |
12 August 2019 | Programme Review for July 2019 - meeting notes |
13 June 2019 | Programme Review for May & June 2019 - meeting notes |
16 May 2019 | Programme Review for April 2019 - meeting notes |
11 April 2019 | Programme Review for March 2019 - meeting notes |
14 March 2019 | Programme Review for February 2019 - meeting notes |
19 February 2019 | Programme Review for January 2019 - meeting notes |
16 January 2019 | Programme Review for November & December 2018 - meeting notes |