Report for January 2021
- Report Date
- January 2021
Report by Muriel Mewissen for Fraser Muir (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
During January, work progressed apace for HSS031 WAMS Business Embedding despite reduced stakeholder availability due to the latest Covid-19 restrictions. This puts the burnt rate slightly higher (62%) than the expected (50%) at mid-year.
Two projects report AMBER:
- HSS031 WAMS Business Embedding due to risk around stakeholder availability
- HSS035 Centre for Open Learning - Migration of CLASS to the cloud due to delay in final checks and sign off from Production, now resolved. This project is expected to formally closed next month.
Therefore, the status of the programme is set to GREEN.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - January 2021
Programme Resource to end of January 2021
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Proposed area for projects this session:
|
CAHSS had a budget of 150 ring fenced days for 20/21. The following allocations have been made, see PRICCL 110:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||
Milestones
RAG StatusGREEN |
Report by Andy Stewart for January 2021Achievements in the Last Period
Issues
Next Steps
|
||||||||||||||||||
RAG StatusAMBER |
Report by Susan Ridder-Patrick for January 2021Achievements in the Last Period
Issues
Next Steps
|
||||||||||||||||||
Xerte Pilot - authorisation and business case
RAG StatusSUSPENDED |
Report by Muriel Mewissen for January 2021Achievements in last period
Next Steps
|
||||||||||||||||||
Centre for Open Learning - Business Process and Systems Review
Will require to be re-planned
RAG StatusGREEN
|
Report by Andy Stewart for January 2021Achievements in the Last Period
Issues
Next Steps
|
||||||||||||||||||
Centre for Open Learning - Migration of CLASS to the cloud
RAG StatusAMBER |
Report by Sophie Izard for January 2021Achievements in last period
Issues
Next steps
|
||||||||||||||||||
Replacement of ECA Mini Portfolios - Business Analysis
RAG StatusGREEN |
Report by Sophie Izard for for January 2021
Issues
Next steps
|
Section Four: Closed Projects
Project Info | Project Manager's Commentary |
---|---|
HSS027 Hope Park Counselling Centre System Implementation | This project was started in August 2018 and was closed on the 6 November 2020. The closure report is available to view. |
This project was started in June 2019 and was closed on the 14 August 2020. The closure report is available to view. |
Section Five: Programme Risk Register
Risk | RAG | Comments |
---|---|---|
Risk 10: Disruption from the current Novel coronavirus (Covid-19) outbreak | RED |
Since 18 March 2020, all staff, as well business partners, moved to working from home during the coronavirus pandemic and UK lockdown which followed on 24 March 2020. Further restrictions were imposed in December 2020 and January 2021. Scotland is now in lockdown under Tier 4 strictest rules. |
Section Six: Programme Meeting Minutes
Date | Comments |
---|---|
25 January 2021 | Programme Review for November & December 2020 |
11 November 2020 | Programme Review for October 2020 - meeting notes |
14 October 2020 | Programme Review for August & September 2020 - meeting notes |
2 September 2020 | Programme Review for July 2020 - meeting notes |
22 July 2020 | Programme Review for June 2020 - meeting notes |
15 June 2020 | Programme Review for May 2020 - meeting notes |
14 May 2020 | Programme Review for April 2020 - meeting notes |
15 April 2020 | Programme Review for March 2020 - meeting notes |
12 March 2020 | Programme Review for January & February 2020 - meeting notes |