Report for May 2021

Report Date
May 2021

Report by Muriel Mewissen for Fraser Muir (Portfolio Owner)

Section One: Programme Commentary, RAG and Resources Update

During May, one project was closed:

The remaining projects are progressing well and on track to close this session.

The status of the programme is set to GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - May 2021

 

 

Programme Resource to end of May 2021

NB: The programme budget has increased by 5 days to support business analysi work in COL to support Timetable for ELE provision, see PRICCL 115.

 

Section Two: Projects Not Started

Project Info Core Funding Budget Allocation

Proposed area for projects this session:

  • None

CAHSS had a budget of 150 ring fenced days for 20/21. The following allocations have been made:

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

HSS015

School of Economics Job Study

 

Milestones

The following milestones are provisional and dependant on the supplier providing the final dataset 

Target Date Title
11-Jun-2021 Job Seeker Development 
30-Jun-2021 Project closure

 

RAG Status

AMBER

Report by Andy Stewart for May 2021

Achievements in the Last Period

  • Job application data has been received and verified in the Test environment.  Arrangements are now in hand to upload the data into the live environment
  • The task to load the remaining in-work data from October 2020 to now has been approved by the supplier 
  • The project sponsor has confirmed no further data will be required after the Job Application data and the remaining in-work data has been loaded

Issues

  • Due to the on-going delays regarding the data supply, the project will require to extend into June to complete the full data uploads 

Next Steps

  • Job Application data to be uploaded to the live environment
  • In-work data covering the period from October 2020 to be uploaded to the live environment 
  • Switch-off the API as data now longer being supplied dynamically 
  • Close project 

RAG Commentary 

The project will require to be extended into June to enable the final data loads to be completed.

HSS031

WAMS Business Embedding

 

Milestones

None

 
RAG Status

CLOSED

Report by Susan Ridder-Patrick for May 2021

Achievements in the Last Period

  • Closure process completed
  • Closure Report completed both for UoE and supplier
  • Lessons Learned document completed

Issues

  • None

Next Steps

  • None

HSS032

Xerte Pilot - authorisation and business case

 

Milestones

Target Date Title
16-Aug-2021 Project suspension ends
 
RAG Status 

SUSPENDED

Report by Muriel Mewissen for May 2021

Achievements in last period

  •  None. Project suspended.

Next Steps

  • Review and unsuspend project in August 2021

HSS037

Replacement of ECA Mini Portfolios - Business Analysis

 

Milestones

Target Date Title
11-Jun-2021 Analysis of possible existing, internal systems
5-Jul-2021 Analysis of ‘off the shelf’ solutions
19-Jul-2021 Validation of need for portfolio submissions
19-Jul-2021 Options appraisal, including costs and impact and recommendation
26-Jul-2021 Project Close
 
RAG Status

GREEN

Report by Muriel Mewissen for May 2021

Achievements in the Last Period

  • Work continue on assessing the suitability of possible solutions already in use at the university in conjunction with LTW.
  • Work continue on researching off the shelf solutions not currently in use at the university. PM talking to external suppliers about quick evaluation.

Issues

  • None

Next Steps

  • Drafting recommentations report

 

Section Four: Closed Projects

Project Info Project Manager's Commentary

HSS031 WAMS Business Embedding

This project was started in September 2019 and was closed on the 21 May 2021. The closure report is available to view.
HSS033 Centre for Open Learning - Business Process and Systems Review This project was started in February 2020 and was closed on the 26 February 2021. The closure report is available to view.
HSS035 Centre for Open Learning - Migration of CLASS to the cloud This project was started in April 2020 and was closed on the 5 February 2021. The closure report is available to view.
HSS027 Hope Park Counselling Centre System Implementation This project was started in August 2018 and was closed on the 6 November 2020. The closure report is available to view.

HSS030 Student Voice Platforms Pilot

This project was started in June 2019 and was closed on the 14 August 2020. The closure report is available to view.

 

Section Five: Programme Risk Register

Risk RAG Comments
Risk 10: Disruption from the current Novel coronavirus (Covid-19) outbreak GREEN

Since 18 March 2020, all staff, as well business partners, moved to working from home during the coronavirus pandemic and UK lockdown which followed on 24 March 2020.

Lockdown restrictions are easing further in Scotland with Edinburgh currently under level 2 of lockdown, with an expectation of a move to level 0 by the end of June 2021 when the WFH as default will end.

Probability and impact of this risk is reduced as restrictions continue to be eased, and the projects in this programme are close to delivery, and less likely to be affected. We expect the programme to be successfully delivered.

 

Section Six: Programme Meeting Minutes

Date Comments
24 May 2021 Programme Review for April 2021
14 April 2021 Programme Review for March 2021
11 March 2021 Programme Review for February 2021
10 February 2021 Programme Review for January 2021
25 January 2021 Programme Review for November & December 2020
11 November 2020 Programme Review for October 2020 - meeting notes 
14 October 2020 Programme Review for August & September 2020 - meeting notes
2 September 2020 Programme Review for July 2020 - meeting notes
22 July 2020 Programme Review for June 2020 - meeting notes
15 June 2020 Programme Review for May 2020 - meeting notes
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.