Report for May 2021
- Report Date
- May 2021
Report by Muriel Mewissen for Fraser Muir (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
During May, one project was closed:
- HSS031 WAMS Business Embedding project closed. The closure report is available to view.
The remaining projects are progressing well and on track to close this session.
The status of the programme is set to GREEN.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - May 2021
Programme Resource to end of May 2021
NB: The programme budget has increased by 5 days to support business analysi work in COL to support Timetable for ELE provision, see PRICCL 115.
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Proposed area for projects this session:
|
CAHSS had a budget of 150 ring fenced days for 20/21. The following allocations have been made:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
MilestonesThe following milestones are provisional and dependant on the supplier providing the final dataset
RAG StatusAMBER |
Report by Andy Stewart for May 2021Achievements in the Last Period
Issues
Next Steps
RAG Commentary The project will require to be extended into June to enable the final data loads to be completed. |
||||||||||||
None RAG StatusCLOSED |
Report by Susan Ridder-Patrick for May 2021Achievements in the Last Period
Issues
Next Steps
|
||||||||||||
Xerte Pilot - authorisation and business case
RAG StatusSUSPENDED |
Report by Muriel Mewissen for May 2021Achievements in last period
Next Steps
|
||||||||||||
Replacement of ECA Mini Portfolios - Business Analysis
RAG StatusGREEN |
Report by Muriel Mewissen for May 2021Achievements in the Last Period
Issues
Next Steps
|
Section Four: Closed Projects
Project Info | Project Manager's Commentary |
---|---|
This project was started in September 2019 and was closed on the 21 May 2021. The closure report is available to view. | |
HSS033 Centre for Open Learning - Business Process and Systems Review | This project was started in February 2020 and was closed on the 26 February 2021. The closure report is available to view. |
HSS035 Centre for Open Learning - Migration of CLASS to the cloud | This project was started in April 2020 and was closed on the 5 February 2021. The closure report is available to view. |
HSS027 Hope Park Counselling Centre System Implementation | This project was started in August 2018 and was closed on the 6 November 2020. The closure report is available to view. |
This project was started in June 2019 and was closed on the 14 August 2020. The closure report is available to view. |
Section Five: Programme Risk Register
Risk | RAG | Comments |
---|---|---|
Risk 10: Disruption from the current Novel coronavirus (Covid-19) outbreak | GREEN |
Since 18 March 2020, all staff, as well business partners, moved to working from home during the coronavirus pandemic and UK lockdown which followed on 24 March 2020. Lockdown restrictions are easing further in Scotland with Edinburgh currently under level 2 of lockdown, with an expectation of a move to level 0 by the end of June 2021 when the WFH as default will end. Probability and impact of this risk is reduced as restrictions continue to be eased, and the projects in this programme are close to delivery, and less likely to be affected. We expect the programme to be successfully delivered. |
Section Six: Programme Meeting Minutes
Date | Comments |
---|---|
24 May 2021 | Programme Review for April 2021 |
14 April 2021 | Programme Review for March 2021 |
11 March 2021 | Programme Review for February 2021 |
10 February 2021 | Programme Review for January 2021 |
25 January 2021 | Programme Review for November & December 2020 |
11 November 2020 | Programme Review for October 2020 - meeting notes |
14 October 2020 | Programme Review for August & September 2020 - meeting notes |
2 September 2020 | Programme Review for July 2020 - meeting notes |
22 July 2020 | Programme Review for June 2020 - meeting notes |
15 June 2020 | Programme Review for May 2020 - meeting notes |