Report for April 2021
- Report Date
- April 2021
Report compiled by Adam Wadee
Section 1: Programme Summary
Programme Manager's Commentary
ISG015 remains Amber this month due to conflicts on PM time. We will look to assign a new PM in order to progress the project to closure.
The next Start of Term project has now started and will confirm the key staff who will be involved with the project this year.
Given that ISG015 remains Amber, the programme RAG is also Amber.
Programme Resource Position
Programme RAG Overview & Forward Look
Section 2: Projects Not Started
Project Info | Programme Manager's Commentary |
|
Section 3: Projects in Progress
Projects |
Project Manager's Commentary |
|||||||||||||||||||||||||||||||||
ISG015 IS Student Recruitment Solution Milestones
RAG Status Amber |
Achievements in Last Period
Issues
Next StepsPriorities include:
|
|||||||||||||||||||||||||||||||||
ISG020 IT and Library Business Service Readiness for Start of Term 21/22 Milestones
RAG Status Green |
Achievements this period
Issues
Next Steps
|
Section 4: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
ISG018 IT and Library Business Service Readiness for Start of Term 20/21 |
Project Closed in December 2020 |
ISG016 Identity and Access Management (IDAM) Strategy |
Project Closed in January 2020 |
ISG017 IT and Library Business Service Readiness for Start of Term 2019/20 |
Project Closed in December 2019 |
ISG009 Alma Library Management Platform 2-Way Feed with E-Financials |
Project Withdrawn in March 2020 |