Report for April 2016

Report Date
April 2016

Report by Susan McKeown for Bruce Nelson (Portfolio Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

The CSCE Programme / Portfolio is overall GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

SCE010 - GREEN - Athena Swan Reporting Improvements project has started and work on the project's Brief is underway.

Although the CSCE projects related to the University's Virtual Edinburgh programme of work (now branded as Edinburgh Cityscope) have been delivered, IS continue to support the Virtual Edinburgh programme through both providing PM Consultancy and support and through work being completed under Innovation project API017 Virtual Edinburgh Foundations which is being funded by the University's CIO. Colleagues can follow this project's progress on its website.

AP56-034 Ring Fenced Allocation for CSCE: Please see section two, Projects Not Started, for proposed use of remaining ring-fenced days in 15/16.

Resources

RAG & Forward Look

Notes on Current Plans for 16/17

  • The work on the Chemistry Scientific Instrument Management Business Case in 14/15 has found that if the recommendations are followed then no work from IS Applications would be needed in 15/16, however potential integration work with Finance and Grouper may be needed in 16/17.
  • As the University Seminar Site is still in pilot phase, and will be until summer 2016, time must be set aside in 16/17 to either turn the pilot into a full service with proper documentation and agreed support levels, or to decommission the site.
  • The Programme Manager attended the College Professional Services Managers Group on 12 April 2016 and has a number of areas of interest noted to investigate for potential use of next year's ring-fenced allocation.
  • The Programme Manager met with those members of the IS IT Consultancy team with constituencies in the College of Science and Engineering to help coordinate efforts across IS

Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary

AP56-034 15/16 Ring Fenced Allocation for CSCE

GREEN

  • The Portfolio Owner has approved the use of the remaining 10 days to complete gap analysis work with the UWP team and the College to help progress the College's use of EdWeb. The programme manager has requested College, UWP and IS resources between May and July to enable this project to be completed.

 

Section Three: Projects in Progress

No current projects in Progress as all started projects have been delivered and closed.

Project InfoProject Managers Commentary

SCE010 (AP56-925)

Athena Swan Reporting Improvements

Category: Discretionary

Milestones

13-May-2016End of Planning
26-Aug-2016Delivery
16-Sep-2016Closure
 

 

RAG Status

GREEN

Report by Susan Duff for April 2016
 

Achievements:

  • New PM assigned
  • Initial meeting with Project Stakeholders held
  • Project Brief started
  • ASTA set up

Issues:

  • None

Next Steps:

  • Project Brief to be completed and signed off
  • End of planning milestone
  • Resources booked in ASTA
  • Review Business Requirements document and complete analysis for Shared Paternity Leave

 

Section Four: Closed or Withdrawn Projects

Project InfoProject Managers Commentary

SCE005 - Virtual Edinburgh Business Case Support

Category: Discretionary

Report by Sheila Fraser

This project was closed on 11-Sep-15.

Please see the Completion Report for further information.

SCE007 - Digitising Scotland Planning

Category: Discretionary

Report by Sheila Fraser

This project was closed on 21-Dec-15

Please see the Completion Report for further information.

SCE008 - University Seminar Site Enhancements Category: Discretionary

Report by Morna Findlay

This project was closed on 15 Jan 16.

Please see the Completion Report for further information.

SCE009 - Virtual Edinburgh Scoping Category: Discretionary

Report by Morna Findlay

This project was closed on 29 Jan 16

Please see the Completion Report for further information.

 

Documentation

Not available.