Report for April 2016
- Report Date
- April 2016
Report by Susan McKeown for Bruce Nelson (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
The CSCE Programme / Portfolio is overall GREEN.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
SCE010 - GREEN - Athena Swan Reporting Improvements project has started and work on the project's Brief is underway.
Although the CSCE projects related to the University's Virtual Edinburgh programme of work (now branded as Edinburgh Cityscope) have been delivered, IS continue to support the Virtual Edinburgh programme through both providing PM Consultancy and support and through work being completed under Innovation project API017 Virtual Edinburgh Foundations which is being funded by the University's CIO. Colleagues can follow this project's progress on its website.
AP56-034 Ring Fenced Allocation for CSCE: Please see section two, Projects Not Started, for proposed use of remaining ring-fenced days in 15/16.
ResourcesRAG & Forward Look
Notes on Current Plans for 16/17
- The work on the Chemistry Scientific Instrument Management Business Case in 14/15 has found that if the recommendations are followed then no work from IS Applications would be needed in 15/16, however potential integration work with Finance and Grouper may be needed in 16/17.
- As the University Seminar Site is still in pilot phase, and will be until summer 2016, time must be set aside in 16/17 to either turn the pilot into a full service with proper documentation and agreed support levels, or to decommission the site.
- The Programme Manager attended the College Professional Services Managers Group on 12 April 2016 and has a number of areas of interest noted to investigate for potential use of next year's ring-fenced allocation.
- The Programme Manager met with those members of the IS IT Consultancy team with constituencies in the College of Science and Engineering to help coordinate efforts across IS
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP56-034 15/16 Ring Fenced Allocation for CSCE GREEN |
|
Section Three: Projects in Progress
No current projects in Progress as all started projects have been delivered and closed.
Project Info | Project Managers Commentary | ||||||
SCE010 (AP56-925)Athena Swan Reporting Improvements Category: Discretionary Milestones
RAG Status GREEN | Report by Susan Duff for April 2016 Achievements:
Issues:
Next Steps:
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
SCE005 - Virtual Edinburgh Business Case SupportCategory: Discretionary | Report by Sheila Fraser This project was closed on 11-Sep-15. Please see the Completion Report for further information. |
SCE007 - Digitising Scotland Planning Category: Discretionary | Report by Sheila Fraser This project was closed on 21-Dec-15 Please see the Completion Report for further information. |
SCE008 - University Seminar Site Enhancements Category: Discretionary | Report by Morna Findlay This project was closed on 15 Jan 16. Please see the Completion Report for further information. |
SCE009 - Virtual Edinburgh Scoping Category: Discretionary | Report by Morna Findlay This project was closed on 29 Jan 16 Please see the Completion Report for further information. |