Report for April 2018
- Report Date
- April 2018
Report by Muriel Mewissen for Victoria Dishon (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
Commentary:
During April, there was no activity in the existing project: SCEP02 Virtual Edinburgh PM Consultancy and Support.
A new PM has been appointed at the end of April to start the following projects:
- SCE012 Supporting for PGT deposits - Requirements
- SCE013 ShareLatex and OverLeaf software trial - Business case support
- SCE014 Creation of a developer community for a College Project Marking Tool
The only ongoing project has the RAG status AMBER due the ongoing uncertainty around the participation in the CityDeal project. The overall status of the CSE programme is AMBER.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - April 2018:
Resources to end April 2018:
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
---|---|
CSE has a budget of 150 ring fenced days for 17/18, possible projects are being considered and allocations yet to be confirmed. |
The College has now reviewed the priority for possible new projects. Several proposals have now been selected and prioritised. Resources availability within ISG is been reviewed to assess how many projects and when these could be scheduled for starting this session. Assignment of PM/BA is still ongoing. 70 days have been assigned to the following projects:
The remaining proposals considered are in the following areas:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary |
SCEP02 Virtual Edinburgh PM Consultancy and Support Category: Discretionary MilestonesN/A
RAG StatusAMBER |
Report by Morna Findlay for April 2018No report provided |
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
SCE011 ExamOnline Trial | This project started in October 2017. This project was closed on 31 August 2017. The Completion Report is now available. |
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
16 April 2018 | Programme Review for March 2018 - meeting notes |
21 March 2018 | Programme Review for February 2018 - meeting notes |
12 February 2018 | Programme Review for December 2017 & January 2018 - meeting notes |
15 January 2018 | Programme Review for November 2017 - meeting notes |
20 November 2017 | Programme Review for October 2017 - meeting notes |
9 November 2017 | Programme Review for September 2017 - meeting notes |
20 September 2017 | Programme Review for August 2017 - meeting notes |
21 Aug 2017 | Programme Review for July 2017 - meeting notes |